Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
ESTW Weschnitztalbahn, KTB, Los 1: Birkenau und Los 2: Rimbach
Reference number: 22FEI63673
II.1.2)Main CPV code
45314300 Installation of cable infrastructure
II.1.3)Type of contract
Works
II.2)Description
II.2.2)Additional CPV code(s)
45314300 Installation of cable infrastructure
II.2.3)Place of performance
NUTS code: DE715 Bergstraße
Main site or place of performance:
II.2.4)Description of the procurement at the time of conclusion of the
contract:
KTB ESTW Weschnitztalbahn Los 2 Rimbach
II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 03/04/2023
End: 03/09/2023
II.2.13)Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds: no
Section V: Award of contract/concession
Contract No: 22FEI63673 _92321712_MKA07
V.2)Award of contract/concession
V.2.1)Date of conclusion of the contract/concession award decision:
13/03/2023
V.2.2)Information about tenders
The contract/concession has been awarded to a group of economic operators: no
V.2.3)Name and address of the contractor/concessionaire
Official name: Friedrich Duensing GmbH Hoch-, Tief- und Eisenbahnbau
Postal address: Kleeblattstraße 2
Town: Neustadt
NUTS code: DE929 Region Hannover
Postal code: 31535
Country: Germany
The contractor/concessionaire is an SME: no
V.2.4)Information on value of the contract/lot/concession (at the time of conclusion
of the contract;excluding VAT)
Total value of the procurement: 436 909.88 EUR
Section VI: Complementary information
VI.3)Additional information:
VI.4)Procedures for review
VI.4.1)Review body
Official name: Vergabekammer des Bundes
Postal address: Villemomblerstr. 76
Town: Bonn
Postal code: 53123
Country: Germany
VI.4.3)Review procedure
Precise information on deadline(s) for review procedures:
Die Geltendmachung der Unwirksamkeit einer Auftragsvergabe in einem Nachprüfungsverfahren ist fristgebunden. Es wird auf die in § 135 Abs. 2 GWB genannten Fristen verwiesen. Nach
§ 135 Abs. 2 S. 2 GWB endet die Frist zur Geltendmachung der Unwirksamkeit 30 Kalendertage nach Veröffentlichung der Bekanntmachung der Auftragsvergabe im Amtsblatt der
Europäischen Union. Nach Ablauf der jeweiligen Frist kann eine Unwirksamkeit nicht mehr festgestellt werden.
VI.5)Date of dispatch of this notice:
01/09/2023
Section VII: Modifications to the contract/concession
VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code
45314300 Installation of cable infrastructure
VII.1.2)Additional CPV code(s)
45314300 Installation of cable infrastructure
VII.1.3)Place of performance
NUTS code: DE715 Bergstraße
Main site or place of performance:
VII.1.4)Description of the procurement:
KTB ESTW Weschnitztalbahn Los 2 Rimbach
VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 03/04/2023
End: 03/09/2023
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)
Total value of the contract/lot/concession: 24 250.00 EUR
VII.1.7)Name and address of the contractor/concessionaire
Official name: Friedrich Duensing GmbH Hoch-, Tief- und Eisenbahnbau
Postal address: Kleeblattstraße 2
Town: Neustadt
NUTS code: DE929 Region Hannover
Postal code: 31535
Country: Germany
The contractor/concessionaire is an SME: no
VII.2)Information about modifications
VII.2.1)Description of the modifications
Nature and extent of the modifications (with indication of possible earlier changes to the contract):
MKA07: Aufgrund Änderungswünsche der ALV werden die SHP im km Bereich 12,5 bis 12,7 umgebaut. Hierzu werden die obersten Platten mit H = 250mm ausgebaut, die Pfosten um das
entfallende Maß nach unten gerammt. Dies erfolgt an 22 bis 23 Feldern. Die dann überzähligen Platten werden in ca. 13 neu herzustellenden Feldern eingebaut in Richtung Rimbach.
VII.2.2)Reasons for modification
Need for additional works, services or supplies by the original contractor/concessionaire (Art. 43(1)(b) of Directive 2014/23/EU, Art. 72(1)(b) of Directive 2014/24/EU, Art. 89(1)(b)
of Directive 2014/25/EU)
Description of the economic or technical reasons and the inconvenience or duplication of cost preventing a change of contractor:
Der Wechsel des Auftragnehmers brächte erhebliche Verzögerungen im Leistungsablauf und der Inbetriebnahme mit sich. Synergieeffekte durch eine einheitliche Leistungsdurchführung
und -betreuung würden verloren gehen und es könnte zu gegenseitigen Behinderungen kommen. Ebenfalls wäre nicht mehr hinreichend erkennbar bei welchem Arbeitnehmer man ggf.
Mängelansprüche geltend machen muss. Manche Positionen könnten auch aus technischen Gründen nicht an einen weiteren AN
weitergegeben werden, da diese Leistungen mit Leistungen aus dem Haupt-LV ineinandergreifen. Die zeitliche Verzögerung, welche mit dem Wechsel des ANs einherginge, hätte enormen
Einfluss auf den geplanten Bauablauf und der damit einhergehenden Inbetriebnahme, was zu erheblichen Schwierigkeiten und Zusatzkosten führen würde.
VII.2.3)Increase in price
Updated total contract value before the modifications (taking into account possible earlier contract modifications and price adaptions and, in the case of Directive 2014/23/EU,
average inflation in the Member State concerned)
Value excluding VAT: 685 159.88 EUR
Total contract value after the modifications
Value excluding VAT: 709 409.88 EUR