Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
Ahrtalbahn, Wiederaufbau KTB
Reference number: 22FEI62025
II.1.2)Main CPV code
45314300 Installation of cable infrastructure
II.1.3)Type of contract
Works
II.2)Description
II.2.2)Additional CPV code(s)
45314300 Installation of cable infrastructure
II.2.3)Place of performance
NUTS code: DEB12 Ahrweiler
Main site or place of performance:
II.2.4)Description of the procurement at the time of conclusion of the
contract:
Los 2; Ahrtalbahn, Wiederaufbau KTB
II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 30/01/2023
End: 30/03/2024
II.2.13)Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds: no
Section V: Award of contract/concession
Contract No: 22FEI62025_92318401_MKA25
Title:
Los 2; Ahrtalbahn, Wiederaufbau KTB
V.2)Award of contract/concession
V.2.1)Date of conclusion of the contract/concession award decision:
20/12/2022
V.2.2)Information about tenders
The contract/concession has been awarded to a group of economic operators: no
V.2.3)Name and address of the contractor/concessionaire
Official name: Geschwister Balter Bauunternehmung GmbH
Postal address: Prümer Straße 46
Town: Losheim/Eif.
NUTS code: DEA28 Euskirchen
Postal code: 53940
Country: Germany
The contractor/concessionaire is an SME: no
V.2.4)Information on value of the contract/lot/concession (at the time of conclusion
of the contract;excluding VAT)
Section VI: Complementary information
VI.3)Additional information:
VI.4)Procedures for review
VI.4.1)Review body
Official name: Vergabekammer des Bundes
Postal address: Villemomblerstr. 76
Town: Bonn
Postal code: 53123
Country: Germany
VI.4.3)Review procedure
Precise information on deadline(s) for review procedures:
Die Geltendmachung der Unwirksamkeit einer Auftragsvergabe in einem Nachprüfungsverfahren ist fristgebunden. Es wird auf die in § 135 Abs. 2 GWB genannten Fristen verwiesen. Nach
§ 135 Abs. 2 S. 2 GWB endet die Frist zur Geltendmachung der Unwirksamkeit 30 Kalendertage nach Veröffentlichung der Bekanntmachung der Auftragsvergabe im Amtsblatt der
Europäischen Union. Nach Ablauf der jeweiligen Frist kann eine Unwirksamkeit nicht mehr festgestellt werden.
VI.5)Date of dispatch of this notice:
07/06/2023
Section VII: Modifications to the contract/concession
VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code
45314300 Installation of cable infrastructure
VII.1.2)Additional CPV code(s)
45314300 Installation of cable infrastructure
VII.1.3)Place of performance
NUTS code: DEB12 Ahrweiler
Main site or place of performance:
VII.1.4)Description of the procurement:
Los 2; Ahrtalbahn, Wiederaufbau KTB
VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 30/01/2023
End: 30/03/2024
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)
VII.1.7)Name and address of the contractor/concessionaire
Official name: Geschwister Balter Bauunternehmung GmbH
Postal address: Prümer Straße 46
Town: Losheim/Eif.
NUTS code: DEA28 Euskirchen
Postal code: 53940
Country: Germany
The contractor/concessionaire is an SME: no
VII.2)Information about modifications
VII.2.1)Description of the modifications
Nature and extent of the modifications (with indication of possible earlier changes to the contract):
MKA25: Los 2 - Gestellung Maschinen und Personal 16./17.05.2023
(Vorläufiger) Wert der Änderung: 4.000,00 EUR (netto)
Frühere Änderungen: Wert insg. 566.765,30 €
VII.2.2)Reasons for modification
Need for modification brought about by circumstances which a diligent contracting authority/entity could not foresee (Art. 43(1)(c) of Directive 2014/23/EU, Art. 72(1)(c) of Directive
2014/24/EU, Art. 89(1)(c) of Directive 2014/25/EU)
Description of the circumstances which rendered the modification necessary and explanation of the unforeseen nature of these circumstances:
Eine Änderung des geplanten Bauablaufs wurde notwendig, da sich die betroffenen BÜ-Anlagen als sehr störanfällig zeigten und auszufallen drohten. Daher mussten diese früher
außer Betrieb gesetzt und gesichert werden um Störungen des Bahnbetriebs zu vermeiden.
VII.2.3)Increase in price