Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
Frankfurt/Main Hbf, Umstrukturierung Nordbau und B-Ebene, Planungsleistungen Lph 5 - 6 und optional Lph 7
Reference number: 14TEI09642
II.1.2)Main CPV code
71200000 Architectural and related services
II.1.3)Type of contract
Services
II.2)Description
II.2.1)Title:
Frankfurt/Main Hbf, Umstrukturierung Nordbau und B-Ebene, Planungsleistungen Lph 5 - 6 und optional Lph 7
II.2.2)Additional CPV code(s)
71240000 Architectural, engineering and planning services
II.2.3)Place of performance
NUTS code: DE712 Frankfurt am Main, Kreisfreie Stadt
II.2.4)Description of the procurement at the time of conclusion of the
contract:
Frankfurt/Main Hbf, Umstrukturierung Nordbau und B-Ebene, Planungsleistungen Lph 5 - 6 und optional Lph
II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 01/08/2014
End: 30/04/2019
II.2.13)Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds: no
Section V: Award of contract/concession
Contract No: 14TEI09642_92219060_NT56
Title:
Frankfurt/Main Hbf, Umstrukturierung Nordbau und B-Ebene, Planungsleistungen Lph 5 - 6 und optional Lph 7
V.2)Award of contract/concession
V.2.1)Date of conclusion of the contract/concession award decision:
29/07/2014
V.2.2)Information about tenders
The contract/concession has been awarded to a group of economic operators: no
V.2.3)Name and address of the contractor/concessionaire
Official name: BIEGE FTG mbH + Schmidt & Pütz GmbH
Postal address: Stühlinger Straße 15
Town: Berlin
NUTS code: DE300 Berlin
Postal code: 10318
Country: Germany
The contractor/concessionaire is an SME: no
V.2.4)Information on value of the contract/lot/concession (at the time of conclusion
of the contract;excluding VAT)
Total value of the procurement: 1.00 EUR
Section VI: Complementary information
VI.3)Additional information:
VI.4)Procedures for review
VI.4.1)Review body
Official name: Vergabekammer des Bundes
Postal address: Villemomblerstr. 76
Town: Bonn
Postal code: 53123
Country: Germany
VI.4.3)Review procedure
Precise information on deadline(s) for review procedures:
Genaue Angaben zu den Fristen für die Einlegung von Rechtsbehelfen:
Die Geltendmachung der Unwirksamkeit einer Auftragsvergabe in einem Nachprüfungsverfahren ist
fristgebunden. Es wird auf die in § 135 Abs. 2 GWB genannten Fristen verwiesen. Nach § 135 Abs. 2 S. 2
GWB endet die Frist zur Geltendmachung der Unwirksamkeit 30 Kalendertage nach Veröffentlichung der
Bekanntmachung der Auftragsvergabe im Amtsblatt der Europäischen Union. Nach Ablauf der jeweiligen Frist
kann eine Unwirksamkeit nicht mehr festgestellt werden.
VI.5)Date of dispatch of this notice:
09/01/2024
Section VII: Modifications to the contract/concession
VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code
71200000 Architectural and related services
VII.1.2)Additional CPV code(s)
71240000 Architectural, engineering and planning services
VII.1.3)Place of performance
NUTS code: DE712 Frankfurt am Main, Kreisfreie Stadt
Main site or place of performance:
VII.1.4)Description of the procurement:
Frankfurt/Main Hbf, Umstrukturierung Nordbau und B-Ebene, Planungsleistungen Lph 5 - 6 und optional Lph
VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 01/08/2014
End: 30/04/2019
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)
Total value of the contract/lot/concession: 1.00 EUR
VII.1.7)Name and address of the contractor/concessionaire
Official name: BIEGE FTG mbH + Schmidt & Pütz GmbH
Postal address: Stühlinger Straße 15
Town: Berlin
NUTS code: DE300 Berlin
Postal code: 10318
Country: Germany
The contractor/concessionaire is an SME: no
VII.2)Information about modifications
VII.2.1)Description of the modifications
Nature and extent of the modifications (with indication of possible earlier changes to the contract):
Nachtrag 56: Die Lage der Entrauchungsöffnungen haben sich geändert. Für die neue Lage ist die Tragwerksplanung im Bereich der
Öffnungen erneut auszuführen, um die mit der nuene Lage verbundenen Randbedingungen zu erfassen und zu berücksichtigen.
Im weiteren hat sich die Menge der Kernbohrungen für die Wand- und Deckendurchführungen erhöht. Die enstprechenden
Nachrechnungen für die Bestandssubstanz ist für die zusätzlichen Kernbohrungen auszuführen.
VII.2.2)Reasons for modification
Need for additional works, services or supplies by the original contractor/concessionaire (Art. 43(1)(b) of Directive 2014/23/EU, Art. 72(1)(b) of Directive 2014/24/EU, Art. 89(1)(b)
of Directive 2014/25/EU)
Description of the economic or technical reasons and the inconvenience or duplication of cost preventing a change of contractor:
Aufgrund der Komplexität und Umfang der Planung führt ein Wechsel des AN zu Verlust der Synergieeffekt und zu zeitlichenZwängen. Im Weiteren ist der AN vollumfänglich in die
bisherige Planung eingebunden und muss sich nicht zeitaufwendig in diesehr komplexen Zusammenhänge der Baumaßnahme und die Örtlichkeiten einarbeiten. Der AN besteht aus
einerPlanungsgemeinschaft zweier Planungsbüros. Ein Wechsel würde die Leistungsbetreuung und Mängelansprüche gegenüber demAN sehr erschweren, eine Klare Schnittstelle ist für
die Nachtragsleistungen gegenüber den Leistungen des Vertrages ist nicht zudefinier. Die Planungen greifen eng ineinader. Ein Wechsel würde zu zeitlichen Zwängen der
Gesamtmaßnahme führen und dieKosten enorm erhöhen.
VII.2.3)Increase in price
Updated total contract value before the modifications (taking into account possible earlier contract modifications and price adaptions and, in the case of Directive 2014/23/EU,
average inflation in the Member State concerned)
Value excluding VAT: 1.00 EUR
Total contract value after the modifications
Value excluding VAT: 1.00 EUR