Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
SPGK_ABS 46/2 Bauzeitliche Kabeltrasse BA 3
Reference number: 22FEI60273
II.1.2)Main CPV code
45231000 Construction work for pipelines, communication and power lines
II.1.3)Type of contract
Works
II.2)Description
II.2.3)Place of performance
NUTS code: DEA1F Wesel
II.2.4)Description of the procurement at the time of conclusion of the
contract:
Los 1
Bauleistung Kabeltiefbau einschl. Ausführungsplanung und Kabelverlegearbeiten
II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 22/08/2022
End: 31/12/2023
II.2.13)Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds: no
Section V: Award of contract/concession
V.2)Award of contract/concession
V.2.1)Date of conclusion of the contract/concession award decision:
31/07/2022
V.2.2)Information about tenders
The contract/concession has been awarded to a group of economic operators: no
V.2.3)Name and address of the contractor/concessionaire
Official name: DB Bahnbau Gruppe GmbH
Postal address: Am Studio 1 A
Town: Berlin
NUTS code: DE300 Berlin
Postal code: 12489
Country: Germany
The contractor/concessionaire is an SME: no
V.2.4)Information on value of the contract/lot/concession (at the time of conclusion
of the contract;excluding VAT)
Total value of the procurement: 2 098 734.05 EUR
Section VI: Complementary information
VI.3)Additional information:
VI.4)Procedures for review
VI.4.1)Review body
Official name: Vergabekammer des Bundes
Postal address: Villemomblerstr. 76
Town: Bonn
Postal code: 53123
Country: Germany
VI.4.3)Review procedure
Precise information on deadline(s) for review procedures:
Genaue Angaben zu den Fristen für die Einlegung von Rechtsbehelfen:
Die Geltendmachung der Unwirksamkeit einer Auftragsvergabe in einem Nachprüfungsverfahren ist fristgebunden. Es wird auf die in § 135 Abs. 2 GWB genannten Fristen verwiesen. Nach
§ 135 Abs. 2 S. 2 GWB endet die Frist zur Geltendmachung der Unwirksamkeit 30 Kalendertage nach Veröffentlichung der Bekanntmachung der Auftragsvergabe im Amtsblatt der
Europäischen Union. Nach Ablauf der jeweiligen Frist kann eine Unwirksamkeit nicht mehr festgestellt werden.
VI.5)Date of dispatch of this notice:
11/12/2023
Section VII: Modifications to the contract/concession
VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code
45231000 Construction work for pipelines, communication and power lines
VII.1.2)Additional CPV code(s)
VII.1.3)Place of performance
NUTS code: DEA1F Wesel
VII.1.4)Description of the procurement:
Los 1
Bauleistung Kabeltiefbau einschl. Ausführungsplanung und Kabelverlegearbeiten
VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 22/08/2022
End: 31/12/2023
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)
Total value of the contract/lot/concession: 2 098 734.05 EUR
VII.1.7)Name and address of the contractor/concessionaire
Official name: DB Bahnbau Gruppe GmbH
Postal address: Am Studio 1 A
Town: Berlin
NUTS code: DE300 Berlin
Postal code: 12489
Country: Germany
The contractor/concessionaire is an SME: no
VII.2)Information about modifications
VII.2.1)Description of the modifications
Nature and extent of the modifications (with indication of possible earlier changes to the contract):
Änderung der teilweisen Ausführung des Kabelkanals, Anpassung von 420 m.
(MKA 01_01)
VII.2.2)Reasons for modification
Need for additional works, services or supplies by the original contractor/concessionaire (Art. 43(1)(b) of Directive 2014/23/EU, Art. 72(1)(b) of Directive 2014/24/EU, Art. 89(1)(b)
of Directive 2014/25/EU)
Description of the economic or technical reasons and the inconvenience or duplication of cost preventing a change of contractor:
Änderung der Ausführung des Kabelkanals auf einem Stück von 420 m von der Variante gemäß LeistungsverzeichnissesPosition 01.09.0040 Kunststoffkabelkanal zu 2/3 erdverlegt
Größe 2 in die Variante Aufgeständerter Kunststoffkabelkanal derGröße 2 mit Deckel inkl. 1,5 m langen feuerverzinkten Stahlstützen.
VII.2.3)Increase in price
Updated total contract value before the modifications (taking into account possible earlier contract modifications and price adaptions and, in the case of Directive 2014/23/EU,
average inflation in the Member State concerned)
Value excluding VAT: 2 230 683.36 EUR
Total contract value after the modifications
Value excluding VAT: 2 255 483.36 EUR