Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
VDE8.11 ABS Nürnberg-Ebensfeld, IBN – Fürther Bogen mit Interimslösung
Reference number: 19FEI41549
II.1.2)Main CPV code
45234100 Railway construction works
II.1.3)Type of contract
Works
II.2)Description
II.2.1)Title:
2.Vergabeeinheit: Leistungspaket 2 OLA, Ziffer 2.1
Lot No: 2
II.2.2)Additional CPV code(s)
45234100 Railway construction works
II.2.3)Place of performance
NUTS code: DE253 Fürth, Kreisfreie Stadt
Main site or place of performance:
II.2.4)Description of the procurement at the time of conclusion of the
contract:
OL-Maste inkl. Gründung 330 Stück; Kettenwerk 12 710 m; OSE Kabel 3 700 m.
II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 09/04/2020
End: 16/12/2022
II.2.13)Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds: no
Section V: Award of contract/concession
Title:
2.Vergabeeinheit: Leistungspaket 2 OLA, Ziffer 2.1
V.2)Award of contract/concession
V.2.1)Date of conclusion of the contract/concession award decision:
24/03/2020
V.2.2)Information about tenders
The contract/concession has been awarded to a group of economic operators: no
V.2.3)Name and address of the contractor/concessionaire
Official name: SPL Powerlines Germany GmbH
Town: Forchheim
NUTS code: DE248 Forchheim
Country: Germany
The contractor/concessionaire is an SME: yes
V.2.4)Information on value of the contract/lot/concession (at the time of conclusion
of the contract;excluding VAT)
Total value of the procurement: 3 963 568.59 EUR
Section VI: Complementary information
VI.3)Additional information:
VI.4)Procedures for review
VI.4.1)Review body
Official name: Vergabekammer des Bundes
Postal address: Villemomblerstr. 76
Town: Bonn
Postal code: 53123
Country: Germany
VI.4.3)Review procedure
Precise information on deadline(s) for review procedures:
Die Geltendmachung der Unwirksamkeit einer Auftragsvergabe in einem Nachprüfungsverfahren ist fristgebunden. Es wird auf die in § 135 Abs. 2 GWB genannten Fristen verwiesen. Nach
§ 135 Abs. 2 S. 2 GWB endet die Frist zur Geltendmachung der Unwirksamkeit 30 Kalendertage nach Veröffentlichung der Bekanntmachung der Auftragsvergabe im Amtsblatt der
Europäischen Union. Nach Ablauf der jeweiligen Frist kann eine Unwirksamkeit nicht mehr festgestellt werden.
VI.5)Date of dispatch of this notice:
08/12/2023
Section VII: Modifications to the contract/concession
VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code
45234100 Railway construction works
VII.1.2)Additional CPV code(s)
VII.1.3)Place of performance
NUTS code: DE253 Fürth, Kreisfreie Stadt
Main site or place of performance:
VII.1.4)Description of the procurement:
OL-Maste inkl. Gründung 330 Stück; Kettenwerk 12 710 m; OSE Kabel 3 700 m.
VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 09/04/2020
End: 16/12/2022
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)
Total value of the contract/lot/concession: 3 963 568.59 EUR
VII.1.7)Name and address of the contractor/concessionaire
Official name: SPL Powerlines Germany GmbH
Town: Forchheim
NUTS code: DE248 Forchheim
Country: Germany
The contractor/concessionaire is an SME: yes
VII.2)Information about modifications
VII.2.1)Description of the modifications
Nature and extent of the modifications (with indication of possible earlier changes to the contract):
MKA 016 - Herstellung und Montage Schalterpodeste Mast 11-11 und 11-13
VII.2.2)Reasons for modification
Need for additional works, services or supplies by the original contractor/concessionaire (Art. 43(1)(b) of Directive 2014/23/EU, Art. 72(1)(b) of Directive 2014/24/EU, Art. 89(1)(b)
of Directive 2014/25/EU)
Description of the economic or technical reasons and the inconvenience or duplication of cost preventing a change of contractor:
Im Rahmen der Ausführung und Abnahmeprüfung wurde festgestellt, dass an den Masten 11-11 (Schalter 202) und 11-13(Schalter W3) die Bedienung der Schalterantrieben aufgrund der
Örtlichkeit nicht regelkonform ist. Durch die Errichtung vonzusätzlichen Schalterpodesten können die Schalter örtlich betätigt werden.Die Erbringung dieser Leistung ist mit den
hauptvertraglich geschuldeten Leistungen technisch und zeitlich eng verzahnt undmuss - auch zur Sicherung von Mangel-/Gewährleistungsansprüchen - vom bereits vor Ort tätigen
Auftragnehmer mit ausgeführtwerden.Die Leistungen sind Voraussetzung für die Übergabe der Anlage an die Instandhaltung, erfolgen diese nicht rechtzeitig ist dieZuweisung der
Instandhaltung gefährdet. Die Maßnahmen dienen der Erfüllung des geschuldeten Werkerfolgs.
VII.2.3)Increase in price
Updated total contract value before the modifications (taking into account possible earlier contract modifications and price adaptions and, in the case of Directive 2014/23/EU,
average inflation in the Member State concerned)
Value excluding VAT: 1 796 070.03 EUR
Total contract value after the modifications
Value excluding VAT: 1 799 570.03 EUR