Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
Planung PfA 7.2 bis 7.4: Autobahnparallele Trasse mit Ausbau Rheintalbahn
Reference number: 15TEI18925
II.1.2)Main CPV code
71311230 Railway engineering services
II.1.3)Type of contract
Services
II.2)Description
II.2.2)Additional CPV code(s)
71322500 Engineering-design services for traffic installations
71327000 Load-bearing structure design services
II.2.3)Place of performance
NUTS code: DE134 Ortenaukreis
II.2.4)Description of the procurement at the time of conclusion of the
contract:
Planung PfA 7.2 bis 7.4: Autobahnparallele Trasse mit Ausbau Rheintalbahn
II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 10/03/2017
End: 01/03/2020
II.2.13)Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds: yes
Identification of the project:
Section V: Award of contract/concession
Title:
Planung PfA 7.2 bis 7.4: Autobahnparallele Trasse mit Ausbau Rheintalbahn
V.2)Award of contract/concession
V.2.1)Date of conclusion of the contract/concession award decision:
11/04/2017
V.2.2)Information about tenders
The contract/concession has been awarded to a group of economic operators: no
V.2.3)Name and address of the contractor/concessionaire
Official name: INGE Schüßler - Plan/ Sweco/ BUNG Mailänder Consult / DB E&C c/o. Schüler- Plan Ing-Ges, Mgh
Town: Frankfurt am Main
NUTS code: DE712 Frankfurt am Main, Kreisfreie Stadt
Country: Germany
The contractor/concessionaire is an SME: no
V.2.4)Information on value of the contract/lot/concession (at the time of conclusion
of the contract;excluding VAT)
Total value of the procurement: 1.00 EUR
Section VI: Complementary information
VI.3)Additional information:
VI.4)Procedures for review
VI.4.1)Review body
Official name: Vergabekammer des Bundes
Postal address: Villemomblerstr. 76
Town: Bonn
Postal code: 53123
Country: Germany
VI.4.3)Review procedure
Precise information on deadline(s) for review procedures:
Die Geltendmachung der Unwirksamkeit einer Auftragsvergabe in einem Nachprüfungsverfahren ist fristgebunden. Es wird auf die in § 135 Abs. 2 GWB genannten Fristen verwiesen. Nach
§ 135 Abs. 2 S. 2 GWB endet die Frist zur Geltendmachung der Unwirksamkeit 30 Kalendertage nach Veröffentlichung der Bekanntmachung der Auftragsvergabe im Amtsblatt der
Europäischen Union. Nach Ablauf der jeweiligen Frist kann eine Unwirksamkeit nicht mehr festgestellt werden.
VI.5)Date of dispatch of this notice:
17/10/2023
Section VII: Modifications to the contract/concession
VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code
71311230 Railway engineering services
VII.1.2)Additional CPV code(s)
71322500 Engineering-design services for traffic installations
71327000 Load-bearing structure design services
VII.1.3)Place of performance
NUTS code: DE134 Ortenaukreis
Main site or place of performance:
Planung PfA 7.2 bis 7.4: Autobahnparallele Trasse mit Ausbau Rheintalbahn
VII.1.4)Description of the procurement:
Planung PfA 7.2 bis 7.4: Autobahnparallele Trasse mit Ausbau Rheintalbahn
VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 10/03/2017
End: 01/03/2020
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)
Total value of the contract/lot/concession: 1.00 EUR
VII.1.7)Name and address of the contractor/concessionaire
Official name: INGE Schüßler - Plan/ Sweco/ BUNG Mailänder Consult / DB E&C c/o. Schüler- Plan Ing-Ges, Mgh
Town: Frankfurt am Main
NUTS code: DE712 Frankfurt am Main, Kreisfreie Stadt
Country: Germany
The contractor/concessionaire is an SME: no
VII.2)Information about modifications
VII.2.1)Description of the modifications
Nature and extent of the modifications (with indication of possible earlier changes to the contract):
LÄA 60 NT 60 : Neuerstellung Planungs-DGM für die ABS, PfA 7.2-7.4
In diesem Nachtrag werden zusätzlich erforderliche Leistungen geltend gemacht, die durch die bahninternen Vorgaben der neuen RiL883 erforderlich sind.
VII.2.2)Reasons for modification
Need for additional works, services or supplies by the original contractor/concessionaire (Art. 43(1)(b) of Directive 2014/23/EU, Art. 72(1)(b) of Directive 2014/24/EU, Art. 89(1)(b)
of Directive 2014/25/EU)
Description of the economic or technical reasons and the inconvenience or duplication of cost preventing a change of contractor:
Dieser Nachtrag ist eine zusätzliche Leistung zu einer im Hauptvertragt festgelegten und von AN geschuldetenLeistung. Der NT 60 kann aus diesem Grund nicht an einen anderen AN
vergebeben werden.
VII.2.3)Increase in price
Updated total contract value before the modifications (taking into account possible earlier contract modifications and price adaptions and, in the case of Directive 2014/23/EU,
average inflation in the Member State concerned)
Value excluding VAT: 1.00 EUR
Total contract value after the modifications
Value excluding VAT: 1.00 EUR