Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
2. S-Bahn-Stammstrecke München, Bauüberwachung VE97c oberirdisch West
Reference number: 20FEI44265
II.1.2)Main CPV code
71240000 Architectural, engineering and planning services
II.1.3)Type of contract
Services
II.2)Description
II.2.2)Additional CPV code(s)
71240000 Architectural, engineering and planning services
II.2.3)Place of performance
NUTS code: DE212 München, Kreisfreie Stadt
II.2.4)Description of the procurement at the time of conclusion of the
contract:
Bauüberwachung Abfallmanagement / Geotechnik
II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 02/11/2020
End: 31/12/2026
II.2.13)Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds: no
Section V: Award of contract/concession
Title:
Bauberwachung Abfallmanagement / Geotechnik
V.2)Award of contract/concession
V.2.1)Date of conclusion of the contract/concession award decision:
16/10/2020
V.2.2)Information about tenders
The contract/concession has been awarded to a group of economic operators: no
V.2.3)Name and address of the contractor/concessionaire
Official name: DB Engineering & Consulting GmbH
Town: München
NUTS code: DE212 München, Kreisfreie Stadt
Country: Germany
The contractor/concessionaire is an SME: no
V.2.4)Information on value of the contract/lot/concession (at the time of conclusion
of the contract;excluding VAT)
Total value of the procurement: 1 471 924.13 EUR
Section VI: Complementary information
VI.3)Additional information:
VI.4)Procedures for review
VI.4.1)Review body
Official name: Vergabekammer des Bundes
Postal address: Villemomblerstr. 76
Town: Bonn
Postal code: 53123
Country: Germany
VI.4.3)Review procedure
Precise information on deadline(s) for review procedures:
Die Geltendmachung der Unwirksamkeit einer Auftragsvergabe in einem Nachprüfungsverfahren ist fristgebunden. Es wird auf die in § 135 Abs. 2 GWB genannten Fristen verwiesen. Nach
§ 135 Abs. 2 S. 2 GWB endet die Frist zur Geltendmachung der Unwirksamkeit 30 Kalendertage nach Veröffentlichung der Bekanntmachung der Auftragsvergabe im Amtsblatt der
Europäischen Union. Nach Ablauf der jeweiligen Frist kann eine Unwirksamkeit nicht mehr festgestellt werden.
VI.5)Date of dispatch of this notice:
14/09/2023
Section VII: Modifications to the contract/concession
VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code
71240000 Architectural, engineering and planning services
VII.1.2)Additional CPV code(s)
71240000 Architectural, engineering and planning services
VII.1.3)Place of performance
NUTS code: DE212 München, Kreisfreie Stadt
Main site or place of performance:
VII.1.4)Description of the procurement:
Bauüberwachung Abfallmanagement / Geotechnik
VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 02/11/2020
End: 31/12/2026
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)
Total value of the contract/lot/concession: 4 250.00 EUR
VII.1.7)Name and address of the contractor/concessionaire
Official name: DB Engineering & Consulting GmbH
Town: München
NUTS code: DE212 München, Kreisfreie Stadt
Country: Germany
The contractor/concessionaire is an SME: no
VII.2)Information about modifications
VII.2.1)Description of the modifications
Nature and extent of the modifications (with indication of possible earlier changes to the contract):
Umwelttechnischer Bericht inkl. tabellarischer Auswertung bei in-situ Beprobungen von Gleisschotter und PSS . LÄ21
VII.2.2)Reasons for modification
Need for additional works, services or supplies by the original contractor/concessionaire (Art. 43(1)(b) of Directive 2014/23/EU, Art. 72(1)(b) of Directive 2014/24/EU, Art. 89(1)(b)
of Directive 2014/25/EU)
Description of the economic or technical reasons and the inconvenience or duplication of cost preventing a change of contractor:
Der zu untersuchende Bereich befindet sich direkt an der 1. Stammstrecke, einem sicherheitskritischen Umfeld. Beengte Platzverhältnisse, Zugverkehr bzw. Baustellenverkehr etc.. Die
Bauüberwachung kennt sich in diesem Bereich bestens aus und kann auch unter den schwierigen dort vorherrschenden Bedingungen diese Art der Arbeiten aufgrund der bereits
ausführlich vorhandenen Ortskenntnisse ausführen. Ein Wechsel des AN würde zu den vorgenannten sicherheitsrelevanten Aspekten zusätzliche Kosten hinsichtlich Sicherung,
Einweisungen etc. verursachen, zudem muss mit weiteren Verzögerungen im Bauablauf gerechnet werden. Die detailliertere Auswertung der Untersuchungsergebnisse erlaubt eine Zuordnung
der einen Untersuchungsparameter und somit eine gezieltere Wahl der Entsorgungsanlage. Letztendlich kann dies zur Reduzierung der Entsorgungskosten beitragen
VII.2.3)Increase in price
Updated total contract value before the modifications (taking into account possible earlier contract modifications and price adaptions and, in the case of Directive 2014/23/EU,
average inflation in the Member State concerned)
Value excluding VAT: 1 482 667.69 EUR
Total contract value after the modifications
Value excluding VAT: 1 486 927.69 EUR