NPP 1220-2023-3068 - Notice of Planned Procurement - Construction - Medium Scale Pipe Protection (Канада - Тендер #48681301) | ||
| ||
| Для перевода текста тендера на нужный язык воспользуйтесь приложением: | ||
Страна: Канада (другие тендеры и закупки Канада) Организатор тендера: www.merx.com Номер конкурса: 48681301 Дата публикации: 30-11-2023 Источник тендера: www.merx.com |
||
00003821449
Issuing OrganizationCity of Abbotsford
Solicitation TypeNPP - Notice of Proposed Procurement (Formal)
Solicitation NumberNPP 1220-2023-3068
TitleNotice of Planned Procurement - Construction - Medium Scale Pipe Protection
Source IDSCRIBE
British Columbia
Purchase TypeNot Stated
2023/11/30 12:52:00 PM EST
Closing Date2023/12/15 05:00:00 PM EST
Purchasing
purchasing@abbotsford.ca
The City of Abbotsford is issuing a Notice of Planned Procurement to advise potential Suppliers that the City plans to conduct a procurement process and is seeking Proponents with experience
acting as the general contractor for a medium scale pipe protection project along the challenging Fraser River or similar locations, with prior work that is the same or similar in nature to
this planned procurement.
Construction is required to complete the repair work at an area of river bed erosion sited on the south and north banks of the Fraser River, east of Beharrell Road and west of Page Road in
Abbotsford, BC. Currently, the erosion has exposed a buried 900mm diameter steel, high pressure, Water Supply Main at the south and north bank. The south section is the highest priority area
and is at significant risk of compromising the supply main and the Matsqui Dyke.
The instream work includes providing a protective cover, and short transition at the upstream and downstream end to bend the new protection into the existing channel. Precise placement of rock
at the south and north exposure, with approximate total of 15,000 tonnage of rock required.
Timelines:
Issue RFP for Construction Work - Week of December 18, 2023
Close RFP for Construction Work - January 17, 2024
Award Contract - January 31, 2024
Start of Construction - February 5, 2024
Completion of Construction - February 29, 2024