Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
Aachen Rothe Erde PFA 2 Bautechnik Los 2.1
Reference number: 18FEI35048
II.1.2)Main CPV code
45221110 Bridge construction work
II.1.3)Type of contract
Works
II.2)Description
II.2.3)Place of performance
NUTS code: DEA2D Städteregion Aachen
Main site or place of performance:
II.2.4)Description of the procurement at the time of conclusion of the
contract:
Oberbau, Gleisverlängerung von ca 1700m (inkl. Erd- und Tiefbau), Anpassung Kreuzungsbauwerk,
Böschungssicherung, Neubau Lärmschutzwände, Koordinierte Kabeltrasse
II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 22/01/2018
End: 28/02/2021
II.2.13)Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds: no
Section V: Award of contract/concession
V.2)Award of contract/concession
V.2.1)Date of conclusion of the contract/concession award decision:
21/01/2019
V.2.2)Information about tenders
The contract/concession has been awarded to a group of economic operators: no
V.2.3)Name and address of the contractor/concessionaire
Official name: Hering Bau GmbH
Postal address: Postfach 624
Town: Burbach
NUTS code: DEA5A Siegen-Wittgenstein
Postal code: 57295
Country: Germany
The contractor/concessionaire is an SME: no
V.2.4)Information on value of the contract/lot/concession (at the time of conclusion
of the contract;excluding VAT)
Total value of the procurement: 16 310 318.70 EUR
Section VI: Complementary information
VI.3)Additional information:
VI.4)Procedures for review
VI.4.1)Review body
Official name: Vergabekammer des Bundes
Postal address: Villemomblerstr. 76
Town: Bonn
Postal code: 53123
Country: Germany
VI.4.3)Review procedure
Precise information on deadline(s) for review procedures:
Genaue Angaben zu den Fristen für die Einlegung von Rechtsbehelfen:
Die Geltendmachung der Unwirksamkeit einer Auftragsvergabe in einem Nachprüfungsverfahren ist fristgebunden. Es wird auf die in § 135 Abs. 2 GWB genannten Fristen verwiesen. Nach
§ 135 Abs. 2 S. 2 GWB endet die Frist zur Geltendmachung der Unwirksamkeit 30 Kalendertage nach Veröffentlichung der Bekanntmachung der Auftragsvergabe im Amtsblatt der
Europäischen Union. Nach Ablauf der jeweiligen Frist kann eine Unwirksamkeit nicht mehr festgestellt werden.
VI.5)Date of dispatch of this notice:
27/11/2023
Section VII: Modifications to the contract/concession
VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code
45221110 Bridge construction work
VII.1.2)Additional CPV code(s)
VII.1.3)Place of performance
NUTS code: DEA23 Köln, Kreisfreie Stadt
Main site or place of performance:
VII.1.4)Description of the procurement:
Oberbau, Gleisverlängerung von ca 1700m (inkl. Erd- und Tiefbau), Anpassung Kreuzungsbauwerk,
Böschungssicherung, Neubau Lärmschutzwände, Koordinierte Kabeltrasse
VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 22/01/2018
End: 28/02/2021
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)
Total value of the contract/lot/concession: 16 310 318.70 EUR
VII.1.7)Name and address of the contractor/concessionaire
Official name: Hering Bau GmbH
Postal address: Postfach 624
Town: Burbach
NUTS code: DEA5A Siegen-Wittgenstein
Postal code: 57295
Country: Germany
The contractor/concessionaire is an SME: no
VII.2)Information about modifications
VII.2.1)Description of the modifications
Nature and extent of the modifications (with indication of possible earlier changes to the contract):
Überarbeitung Böschung
(MKA 203_85)
VII.2.2)Reasons for modification
Need for modification brought about by circumstances which a diligent contracting authority/entity could not foresee (Art. 43(1)(c) of Directive 2014/23/EU, Art. 72(1)(c) of Directive
2014/24/EU, Art. 89(1)(c) of Directive 2014/25/EU)
Description of the circumstances which rendered the modification necessary and explanation of the unforeseen nature of these circumstances:
Die Starkregenereignisse im Juli 2021 hatten zur Folge, dass die bereits fertiggestellte Böschung an Gleis 113 in den Bereichen km 66,88 und km 66,0 punktuell beschädigt worden
ist. Vor diesem Hintergrund mussten in diesen Bereichen die Profilierung der Tragschicht als auch die Profilierung mit belebter Bodenschicht zwingend vor der Inbetriebnahme im Juli
2023 überarbeitet werden. Diese zusätzliche Leistung ist auf ein unerwartetes Ereignis ausgelöst durch höhere Gewalt zurückzuführen und konnte im Hauptvertrag nicht
berücksichtigt werden.
VII.2.3)Increase in price
Updated total contract value before the modifications (taking into account possible earlier contract modifications and price adaptions and, in the case of Directive 2014/23/EU,
average inflation in the Member State concerned)
Value excluding VAT: 26 640 603.95 EUR
Total contract value after the modifications
Value excluding VAT: 26 660 603.95 EUR