Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
Planung ESTW Strecke 1271 - Kapazitätserhöhung S3, S31, S32, Lph 3-4, optional Lph 5-7, 9
Reference number: 20FEI46379
II.1.2)Main CPV code
71322500 Engineering-design services for traffic installations
II.1.3)Type of contract
Services
II.2)Description
II.2.3)Place of performance
NUTS code: DE600 Hamburg
II.2.4)Description of the procurement at the time of conclusion of the
contract:
Planung ESTW Strecke 1271 - Kapazitätserhöhung S3, S31, S32, Lph 3-4,
II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Duration in days: 1
II.2.13)Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds: no
Section V: Award of contract/concession
Title:
Planung ESTW Strecke 1271 - Kapazitätserhöhung S3, S31, S32, Lph 3-4, optional Lph 5-7, 9
V.2)Award of contract/concession
V.2.1)Date of conclusion of the contract/concession award decision:
15/01/2021
V.2.2)Information about tenders
The contract/concession has been awarded to a group of economic operators: no
V.2.3)Name and address of the contractor/concessionaire
Official name: DB Engineering & Consulting Planung
Town: Hamburg
NUTS code: DE600 Hamburg
Country: Germany
The contractor/concessionaire is an SME: no
V.2.4)Information on value of the contract/lot/concession (at the time of conclusion
of the contract;excluding VAT)
Total value of the procurement: 646 960.34 EUR
Section VI: Complementary information
VI.3)Additional information:
VI.4)Procedures for review
VI.4.1)Review body
Official name: Vergabekammer des Bundes
Postal address: Villemomblerstr. 76
Town: Bonn
Postal code: 53123
Country: Germany
VI.4.3)Review procedure
Precise information on deadline(s) for review procedures:
Die Geltendmachung der Unwirksamkeit einer Auftragsvergabe in einem Nachprüfungsverfahren ist fristgebunden. Es wird auf die in § 135 Abs. 2 GWB genannten Fristen verwiesen. Nach
§ 135 Abs. 2 S. 2 GWB endet die Frist zur Geltendmachung der Unwirksamkeit 30 Kalendertage nach Veröffentlichung der Bekanntmachung der Auftragsvergabe im Amtsblatt der
Europäischen Union. Nach Ablauf der jeweiligen Frist kann eine Unwirksamkeit nicht mehr festgestellt werden.
VI.5)Date of dispatch of this notice:
24/10/2023
Section VII: Modifications to the contract/concession
VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code
71322500 Engineering-design services for traffic installations
VII.1.2)Additional CPV code(s)
71322500 Engineering-design services for traffic installations
VII.1.3)Place of performance
NUTS code: DE600 Hamburg
VII.1.4)Description of the procurement:
Planung ESTW Strecke 1271 - Kapazitätserhöhung S3, S31, S32, Lph 3-4,
VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Duration in days: 1
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)
Total value of the contract/lot/concession: 646 960.34 EUR
VII.1.7)Name and address of the contractor/concessionaire
Official name: DB Engineering & Consulting Planung
Town: Hamburg
NUTS code: DE600 Hamburg
Country: Germany
The contractor/concessionaire is an SME: no
VII.2)Information about modifications
VII.2.1)Description of the modifications
Nature and extent of the modifications (with indication of possible earlier changes to the contract):
Nachtrag 14: Gebäude Hausbruch, DB E&C/Bekanntmachung
Aufgrund eines unerwartet hohen Platzbedarfs im Stellwerk Hausbruch, kann die neue Technik nicht untergebracht werden. Um
dies realisieren zu können, soll ein neues ESTW-Z Modulgebäude sowie eine Netzersatzanlage auf Fremdgrund neben dem
Altbestand geplant werden. Dies Planungsleistung ist zur Erfüllung des ursprünglichen Vertrages notwendig.
VII.2.2)Reasons for modification
Need for additional works, services or supplies by the original contractor/concessionaire (Art. 43(1)(b) of Directive 2014/23/EU, Art. 72(1)(b) of Directive 2014/24/EU, Art. 89(1)(b)
of Directive 2014/25/EU)
Description of the economic or technical reasons and the inconvenience or duplication of cost preventing a change of contractor:
Die DB E&C ist mit der Umsetzung der Leistungsphasen 3&4 beauftragt, innerhalb welcher sie bereits die Anpassung desbesehenden Stellwerkgebäudes im Planungsumfang hat.
Dabei wurde seitens der DB E&C bereits ein Raumprogramm erarbeitet,welches aufgezeigt hat, dass der Platzbedarf im bestehenden Gebäude nicht mehr auskömmlich ist. Die dabei
bereitserarbeiteten Erkenntnisse hinsichtlich der räumlichen Ausgestaltung samt Platzbedarf, kann die DB E&C effizient auf die Planungdes neuen ESTW-Z Gebäudes übertragen.
Bei einem Wechsel des AN gingen diese Synergieeffekte verloren.
VII.2.3)Increase in price
Updated total contract value before the modifications (taking into account possible earlier contract modifications and price adaptions and, in the case of Directive 2014/23/EU,
average inflation in the Member State concerned)
Value excluding VAT: 765 520.00 EUR
Total contract value after the modifications
Value excluding VAT: 763 753.91 EUR