Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
ABS/NBS Ulm – Augsburg – Vorplanungsleistung Lph 1-2
Reference number: 21FEI52781
II.1.2)Main CPV code
71240000 Architectural, engineering and planning services
II.1.3)Type of contract
Services
II.2)Description
II.2.2)Additional CPV code(s)
71240000 Architectural, engineering and planning services
II.2.3)Place of performance
NUTS code: DE144 Ulm, Stadtkreis
Main site or place of performance:
II.2.4)Description of the procurement at the time of conclusion of the
contract:
II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 01/08/2022
End: 13/12/2024
II.2.13)Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds: no
Section V: Award of contract/concession
V.2)Award of contract/concession
V.2.1)Date of conclusion of the contract/concession award decision:
25/07/2022
V.2.2)Information about tenders
The contract/concession has been awarded to a group of economic operators: yes
V.2.3)Name and address of the contractor/concessionaire
Official name: Sweco GmbH
Town: Frankfurt am Main
NUTS code: DE712 Frankfurt am Main, Kreisfreie Stadt
Country: Germany
The contractor/concessionaire is an SME: no
V.2.3)Name and address of the contractor/concessionaire
Official name: Schüssler-Plan Ingenieurgesellschaft mbH
Town: Frankfurt am Main
NUTS code: DE712 Frankfurt am Main, Kreisfreie Stadt
Country: Germany
The contractor/concessionaire is an SME: no
V.2.3)Name and address of the contractor/concessionaire
Official name: SSF Ingenieure AG
Town: München
NUTS code: DE212 München, Kreisfreie Stadt
Country: Germany
The contractor/concessionaire is an SME: no
V.2.4)Information on value of the contract/lot/concession (at the time of conclusion
of the contract;excluding VAT)
Section VI: Complementary information
VI.3)Additional information:
VI.4)Procedures for review
VI.4.1)Review body
Official name: Vergabekammer des Bundes
Postal address: Villemomblerstr. 76
Town: Bonn
Postal code: 53123
Country: Germany
VI.4.3)Review procedure
Precise information on deadline(s) for review procedures:
Die Geltendmachung der Unwirksamkeit einer Auftragsvergabe in einem Nachprüfungsverfahren ist fristgebunden. Es wird auf die in § 135 Abs. 2 GWB genannten Fristen verwiesen. Nach
§ 135 Abs. 2 S. 2 GWB endet die Frist zur Geltendmachung der Unwirksamkeit 30 Kalendertage nach Veröffentlichung der Bekanntmachung der Auftragsvergabe im Amtsblatt der
Europäischen Union. Nach Ablauf der jeweiligen Frist kann eine Unwirksamkeit nicht mehr festgestellt werden.
VI.5)Date of dispatch of this notice:
17/10/2023
Section VII: Modifications to the contract/concession
VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code
71240000 Architectural, engineering and planning services
VII.1.2)Additional CPV code(s)
71240000 Architectural, engineering and planning services
VII.1.3)Place of performance
NUTS code: DE144 Ulm, Stadtkreis
Main site or place of performance:
VII.1.4)Description of the procurement:
VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 01/08/2022
End: 13/12/2024
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)
VII.1.7)Name and address of the contractor/concessionaire
Official name: Sweco GmbH
Town: Frankfurt
NUTS code: DE712 Frankfurt am Main, Kreisfreie Stadt
Country: Germany
The contractor/concessionaire is an SME: no
VII.1.7)Name and address of the contractor/concessionaire
Official name: Schüssler-Plan Ingenieurgesellschaft mbH
Town: Frankfurt
NUTS code: DE712 Frankfurt am Main, Kreisfreie Stadt
Country: Germany
The contractor/concessionaire is an SME: no
VII.1.7)Name and address of the contractor/concessionaire
Official name: SSF Ingenieure AG
Town: München
NUTS code: DE212 München, Kreisfreie Stadt
Country: Germany
The contractor/concessionaire is an SME: no
VII.2)Information about modifications
VII.2.1)Description of the modifications
Nature and extent of the modifications (with indication of possible earlier changes to the contract):
Im Hauptvertrag enthalten sind die Erstellung des Bestandsmodells der bestehenden Eisenbahnverkehrsanlagen.
Weiterhin soll im Zuge der Leistung die Auswirkung der geplanten Oberleitung auf bestehendeOberleitungsanlagen, Bauwerke und Zwangspunkte geprüft werden um die Auswirkungen der
Vorplanung auf die Bestandsinfrastruktur abschätzen zu können.
Dies Betrifft die Bestandsbereiche Augsburg-Dinkelscherben ;
Burgau und von Unterfahlheim bis Neu-Ulm.
Im Zuge der weiteren Planungen hat sich nach Sicht des AN ergeben, dass die Bestansmodellierung der Oberleitungsanlagen relevant für eine tragfähige und funktionale Planung sind,
da nur so die Kosten und zeitlichen Aufwendungen in die Vorplanung einfließen können .
In den vertraglich geschuldeten Trassenplanungen hat sich die Notwendigkeit durch die Optimierung der Trasse ergeben die oben genannten Bereiche der Bestandsoberleitung zu
modellieren. Die Auswirkungen auf Kosten und Termine auf die Bestandsoberleitung sind sonst nicht abzuschätzen und nur so wirtschaftlich darstellbar, da nur so die Abhängigkeiten
und optimierungen der Bauwerkslage und die optimale Lage der neuen Oberleitungsanlage an die angepasste Trassierung erfolgen kann. Hier handelt es sich um einen interativen Prozess.
LÄ 6 Violett Durchlässe
VII.2.2)Reasons for modification
Need for additional works, services or supplies by the original contractor/concessionaire (Art. 43(1)(b) of Directive 2014/23/EU, Art. 72(1)(b) of Directive 2014/24/EU, Art. 89(1)(b)
of Directive 2014/25/EU)
Description of the economic or technical reasons and the inconvenience or duplication of cost preventing a change of contractor:
Die Leistung Modellierung Bestandsoberleitungsanlagen ist für das vertraglich geschuldete Ergebnis notwendig. Die zu erzielenden Erkenntnisse sind übergreifend nur durch den
Generalplaner Lph 1/2 zu erfassen und zu bewerten.
Der Grund liegt in der Abhängigkeiten und Verzahnung der Planung der neuen Oberleitung mit der Bestandsoberleitung und den optimiertrungen der Ingenieurbauwerke für das
BIM-Gesamtmodell
VII.2.3)Increase in price