Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
Kabeltiefbaumaßnahmen für das ESTW-R Berchtesgadener Land
Reference number: 19FEI40910
II.1.2)Main CPV code
45200000 Works for complete or part construction and civil engineering work
II.1.3)Type of contract
Works
II.2)Description
II.2.2)Additional CPV code(s)
45200000 Works for complete or part construction and civil engineering work
II.2.3)Place of performance
NUTS code: DE215 Berchtesgadener Land
II.2.4)Description of the procurement at the time of conclusion of the
contract:
Kabeltiefbau Abschnitt Bischofswiesen – Berchtesgaden
(Strecke 5741 km 10,256 BÜ Schöndorfer – km 19,128 Berchtesgaden)
II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 06/03/2020
End: 31/12/2023
II.2.13)Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds: no
Section V: Award of contract/concession
Title:
Kabeltiefbau Abschnitt Bischofswiesen – Berchtesgaden (Strecke 5741 km 10,256 B Schndorfer – km 19,128 Berchtesgaden)
V.2)Award of contract/concession
V.2.1)Date of conclusion of the contract/concession award decision:
24/02/2020
V.2.2)Information about tenders
The contract/concession has been awarded to a group of economic operators: yes
V.2.3)Name and address of the contractor/concessionaire
Official name: Swietelsky Bau GmbH
Town: München
NUTS code: DE212 München, Kreisfreie Stadt
Country: Germany
The contractor/concessionaire is an SME: no
V.2.3)Name and address of the contractor/concessionaire
Official name: Ing. Hans Bodner Baugesellschaft mbH
Town: Wals
NUTS code: AT32 Salzburg
Country: Austria
The contractor/concessionaire is an SME: no
V.2.4)Information on value of the contract/lot/concession (at the time of conclusion
of the contract;excluding VAT)
Total value of the procurement: 2 966 266.66 EUR
Section VI: Complementary information
VI.3)Additional information:
VI.4)Procedures for review
VI.4.1)Review body
Official name: Vergabekammer des Bundes
Postal address: Villemomblerstr. 76
Town: Bonn
Postal code: 53123
Country: Germany
VI.4.3)Review procedure
Precise information on deadline(s) for review procedures:
Die Geltendmachung der Unwirksamkeit einer Auftragsvergabe in einem Nachprüfungsverfahren ist fristgebunden. Es wird auf die in § 135 Abs. 2 GWB genannten Fristen verwiesen. Nach
§ 135 Abs. 2 S. 2 GWB endet die Frist zur Geltendmachung der Unwirksamkeit 30 Kalendertage nach Veröffentlichung der Bekanntmachung der Auftragsvergabe im Amtsblatt der
Europäischen Union. Nach Ablauf der jeweiligen Frist kann eine Unwirksamkeit nicht mehr festgestellt werden.
VI.5)Date of dispatch of this notice:
22/09/2023
Section VII: Modifications to the contract/concession
VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code
45200000 Works for complete or part construction and civil engineering work
VII.1.2)Additional CPV code(s)
45200000 Works for complete or part construction and civil engineering work
VII.1.3)Place of performance
NUTS code: DE215 Berchtesgadener Land
Main site or place of performance:
VII.1.4)Description of the procurement:
Kabeltiefbau Abschnitt Bischofswiesen – Berchtesgaden
(Strecke 5741 km 10,256 BÜ Schöndorfer – km 19,128 Berchtesgaden)
VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 06/03/2020
End: 31/12/2023
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)
Total value of the contract/lot/concession: 2 966 266.66 EUR
VII.1.7)Name and address of the contractor/concessionaire
Official name: Arge KT - BGL C/O. Swietelsky Baugesellschaft mbH
Postal address: Landsbergerstraße 480
Town: München
NUTS code: DE212 München, Kreisfreie Stadt
Country: Germany
The contractor/concessionaire is an SME: no
VII.2)Information about modifications
VII.2.1)Description of the modifications
Nature and extent of the modifications (with indication of possible earlier changes to the contract):
15 - Asphaltierarbeiten BGD BHF bei der Strecke 5741
VII.2.2)Reasons for modification
Need for additional works, services or supplies by the original contractor/concessionaire (Art. 43(1)(b) of Directive 2014/23/EU, Art. 72(1)(b) of Directive 2014/24/EU, Art. 89(1)(b)
of Directive 2014/25/EU)
Description of the economic or technical reasons and the inconvenience or duplication of cost preventing a change of contractor:
Im Zuge der VOB Abnahme wurden auf der Strecke diverse Zusatzarbeiten angeordnet: Mm Bhf Berchtesgaden müssen
diverse Flächen asphaltiert werden sowie Absperrpfosten und Absperrketten montiert werden.
VII.2.3)Increase in price
Updated total contract value before the modifications (taking into account possible earlier contract modifications and price adaptions and, in the case of Directive 2014/23/EU,
average inflation in the Member State concerned)
Value excluding VAT: 6 338 939.99 EUR
Total contract value after the modifications
Value excluding VAT: 6 355 259.38 EUR