Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
Bautechnische Leistungen Korridor RiedbahnLos1: Bauabschnitt 1 Mannheim–Waldhof – LampertheimLos2: Bauabschnitt 2 Biblis – GernsheimLos3: Bauabschnitt 3 Riedstadt-Goddelau –
Mörfelden - Walldorf
Reference number: 21FEI51048
II.1.2)Main CPV code
45234116 Track construction works
II.1.3)Type of contract
Works
II.2)Description
II.2.2)Additional CPV code(s)
45234116 Track construction works
II.2.3)Place of performance
NUTS code: DE717 Groß-Gerau
Main site or place of performance:
II.2.4)Description of the procurement at the time of conclusion of the
contract:
Bauabschnitt 2 Biblis – Gernsheim
II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 07/10/2021
End: 31/12/2025
II.2.13)Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds: no
Section V: Award of contract/concession
Contract No: 21FEI51048_92303633_NT049
Title:
Bauabschnitt 2 Biblis – Gernsheim
V.2)Award of contract/concession
V.2.1)Date of conclusion of the contract/concession award decision:
11/10/2021
V.2.2)Information about tenders
The contract/concession has been awarded to a group of economic operators: no
V.2.3)Name and address of the contractor/concessionaire
Official name: Leonhard Weiss GmbH & Co.KG
Postal address: Leonhard-Weiss-Straße 2-3
Town: Satteldorf
NUTS code: DE11A Schwäbisch Hall
Postal code: 74589
Country: Germany
The contractor/concessionaire is an SME: no
V.2.4)Information on value of the contract/lot/concession (at the time of conclusion
of the contract;excluding VAT)
Section VI: Complementary information
VI.3)Additional information:
VI.4)Procedures for review
VI.4.1)Review body
Official name: Vergabekammer des Bundes
Postal address: Villemomblerstr. 76
Town: Bonn
Postal code: 53123
Country: Germany
VI.4.3)Review procedure
Precise information on deadline(s) for review procedures:
Die Geltendmachung der Unwirksamkeit einer Auftragsvergabe in einem Nachprüfungsverfahren ist fristgebunden. Es wird auf die in § 135 Abs. 2 GWB genannten Fristen verwiesen. Nach
§ 135 Abs. 2 S. 2 GWB endet die Frist zur Geltendmachung der Unwirksamkeit 30 Kalendertage nach Veröffentlichung der Bekanntmachung der Auftragsvergabe im Amtsblatt der
Europäischen Union. Nach Ablauf der jeweiligen Frist kann eine Unwirksamkeit nicht mehr festgestellt werden.
VI.5)Date of dispatch of this notice:
23/08/2023
Section VII: Modifications to the contract/concession
VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code
45234116 Track construction works
VII.1.2)Additional CPV code(s)
45234116 Track construction works
VII.1.3)Place of performance
NUTS code: DE717 Groß-Gerau
Main site or place of performance:
VII.1.4)Description of the procurement:
Bauabschnitt 2 Biblis – Gernsheim
VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 07/10/2021
End: 31/12/2025
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)
VII.1.7)Name and address of the contractor/concessionaire
Official name: Leonhard Weiss GmbH & Co.KG
Postal address: Leonhard-Weiss-Straße 2-3
Town: Satteldorf
NUTS code: DE11A Schwäbisch Hall
Postal code: 74589
Country: Germany
The contractor/concessionaire is an SME: no
VII.2)Information about modifications
VII.2.1)Description of the modifications
Nature and extent of the modifications (with indication of possible earlier changes to the contract):
Nachtrag 049: MKA049 Zusatzmaßnahmen an Reptilienschutzzäunen BA 02 gem. Vorgaben LBP, UNB und UBÜW
VII.2.2)Reasons for modification
Need for additional works, services or supplies by the original contractor/concessionaire (Art. 43(1)(b) of Directive 2014/23/EU, Art. 72(1)(b) of Directive 2014/24/EU, Art. 89(1)(b)
of Directive 2014/25/EU)
Description of the economic or technical reasons and the inconvenience or duplication of cost preventing a change of contractor:
Im Rahmen von Freischnittarbeiten für die Herrichtung von BE-Flächen werden zusätzlich der Rückbau und die Entsorgung von Reptilienschutzzäunen und 2 Vergrähmungsmahden am
Ende der vertraglichen Bauzeit notwendig. Die zusätzlichen Leistungen sind erst im Rahmen der Umweltplanung bekannt geworden und von der umweltfachlichen Bauüberwachung, bzw.
durch die Vorgaben aus der LBP und der UNB sowie der UBÜW gefordert. Der AN ist bereits mit Personal und Gerät vor Ort. Der AN ist bereits zur Leistungsdurchführung von
Freischnittarbeiten der Kabeltrassen und zur Erstellung von Schutzzäunen vor Ort. Ein AN-Wechsel würde zu Zusatzkosten führen, da Synergieeffekte verloren gehen. Außerdem würde
ein AN-Wechsel zusätzlich Zeit in Anspruch nehmen, wodurch es zu Verzögerungen im Leistungsablauf kommen würde.
VII.2.3)Increase in price