Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
ABS Niebüll-Klanxbüll (-Westerland) - Sicherungsleistungen für Baugrunderkundung
Reference number: 22FEI59933
II.1.2)Main CPV code
79710000 Security services
II.1.3)Type of contract
Services
II.2)Description
II.2.2)Additional CPV code(s)
79710000 Security services
II.2.3)Place of performance
NUTS code: DEF07 Nordfriesland
Main site or place of performance:
II.2.4)Description of the procurement at the time of conclusion of the
contract:
Sicherungsleistungen für Baugrunderkundung
II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Duration in days: 1
II.2.13)Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds: no
Section V: Award of contract/concession
Title:
ABS Niebüll-Klanxbüll (-Westerland) - Sicherungsleistungen für Baugrunderkundung
V.2)Award of contract/concession
V.2.1)Date of conclusion of the contract/concession award decision:
26/08/2022
V.2.2)Information about tenders
The contract/concession has been awarded to a group of economic operators: no
V.2.3)Name and address of the contractor/concessionaire
Official name: AMR Gleissicherung GmbH
Town: Gelsenkirchen
NUTS code: DEA32 Gelsenkirchen, Kreisfreie Stadt
Country: Germany
The contractor/concessionaire is an SME: no
V.2.4)Information on value of the contract/lot/concession (at the time of conclusion
of the contract;excluding VAT)
Total value of the procurement: 129 546.00 EUR
Section VI: Complementary information
VI.3)Additional information:
Wir weisen darauf hin, dass die VO (EU) 2022/576 zur Änderung der VO (EU) Nr. 833/2014 Anwendung
findet und Unternehmen, die den Sanktionsmaßnahmen in Art. 5k der VO (EU) 2022/576 unterfallen, aus dem
Vergabeverfahren ausgeschlossen werden.
VI.4)Procedures for review
VI.4.1)Review body
Official name: Vergabekammer des Bundes
Postal address: Villemomblerstr. 76
Town: Bonn
Postal code: 53123
Country: Germany
VI.4.3)Review procedure
Precise information on deadline(s) for review procedures:
Genaue Angaben zu den Fristen für die Einlegung von Rechtsbehelfen:
Die Geltendmachung der Unwirksamkeit einer Auftragsvergabe in einem Nachprüfungsverfahren ist
fristgebunden. Es wird auf die in § 135 Abs. 2 GWB genannten Fristen verwiesen. Nach § 135 Abs. 2 S. 2
GWB endet die Frist zur Geltendmachung der Unwirksamkeit 30 Kalendertage nach Veröffentlichung der
Bekanntmachung der Auftragsvergabe im Amtsblatt der Europäischen Union. Nach Ablauf der jeweiligen Frist
kann eine Unwirksamkeit nicht mehr festgestellt werden.
VI.5)Date of dispatch of this notice:
12/07/2023
Section VII: Modifications to the contract/concession
VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code
79710000 Security services
VII.1.2)Additional CPV code(s)
79710000 Security services
VII.1.3)Place of performance
NUTS code: DEF07 Nordfriesland
Main site or place of performance:
VII.1.4)Description of the procurement:
Sicherungsleistungen für Baugrunderkundung
VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Duration in days: 1
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)
Total value of the contract/lot/concession: 129 546.00 EUR
VII.1.7)Name and address of the contractor/concessionaire
Official name: AMR Gleissicherung GmbH
Town: Gelsenkirchen
NUTS code: DEA32 Gelsenkirchen, Kreisfreie Stadt
Country: Germany
The contractor/concessionaire is an SME: no
VII.2)Information about modifications
VII.2.1)Description of the modifications
Nature and extent of the modifications (with indication of possible earlier changes to the contract):
NT02 - Nutzung ATWS aufgrund angepasster RIL132 (Abschnitt 1)
VII.2.2)Reasons for modification
Need for modification brought about by circumstances which a diligent contracting authority/entity could not foresee (Art. 43(1)(c) of Directive 2014/23/EU, Art. 72(1)(c) of Directive
2014/24/EU, Art. 89(1)(c) of Directive 2014/25/EU)
Description of the circumstances which rendered the modification necessary and explanation of the unforeseen nature of these circumstances:
Aufgrund einer Regelwerksanpassung (RIL 132) (16.01.2023) sind Veränderungen im "Rimini" vorgenommen worden (Auswahlprozess für Sicherungsmaßnahmen). Hierdurch wurde der Einsatz
von Sicherungsposten weiter beschränkt, weshalb der Einsatz einer ATWS notwendig ist. Diese Regelewerksanpassung ist erst nach dem Zeitpunkt der Vergabe (09/2022) sowie dem Beginn
der Arbeiten (10/2022) umgesetzt worden. Der Gesamtcharakter des Auftrages bleibt mit dieser Nachtragsleistung unverändert. Der AN führt die eingetakteten Sicherungsleistungen
für die Baugrunderkundung durch. Bei dem Nachtrag handelt es sich um eine notwendige Anpassung der Sicherung.
VII.2.3)Increase in price
Updated total contract value before the modifications (taking into account possible earlier contract modifications and price adaptions and, in the case of Directive 2014/23/EU,
average inflation in the Member State concerned)
Value excluding VAT: 270 710.20 EUR
Total contract value after the modifications
Value excluding VAT: 428 870.20 EUR