Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
ESTW-R Schliersee/ESTW-R Bayrischzell,BÜW
Reference number: 20FEI48119
II.1.2)Main CPV code
71240000 Architectural, engineering and planning services
II.1.3)Type of contract
Services
II.2)Description
II.2.2)Additional CPV code(s)
71240000 Architectural, engineering and planning services
II.2.3)Place of performance
NUTS code: DE21F Miesbach
Main site or place of performance:
II.2.4)Description of the procurement at the time of conclusion of the
contract:
II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 15/02/2021
End: 30/06/2022
II.2.13)Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds: no
Section V: Award of contract/concession
V.2)Award of contract/concession
V.2.1)Date of conclusion of the contract/concession award decision:
01/02/2021
V.2.2)Information about tenders
The contract/concession has been awarded to a group of economic operators: yes
V.2.3)Name and address of the contractor/concessionaire
Official name: R&K Ingenieure GmbH
Town: Walow
NUTS code: DE80J Mecklenburgische Seenplatte
Country: Germany
The contractor/concessionaire is an SME: yes
V.2.3)Name and address of the contractor/concessionaire
Official name: PTB Magdeburg GmbH
Town: Magdeburg
NUTS code: DEE03 Magdeburg, Kreisfreie Stadt
Country: Germany
The contractor/concessionaire is an SME: yes
V.2.4)Information on value of the contract/lot/concession (at the time of conclusion
of the contract;excluding VAT)
Section VI: Complementary information
VI.3)Additional information:
VI.4)Procedures for review
VI.4.1)Review body
Official name: Vergabekammer des Bundes
Postal address: Villemomblerstr. 76
Town: Bonn
Postal code: 53123
Country: Germany
VI.4.3)Review procedure
Precise information on deadline(s) for review procedures:
Die Geltendmachung der Unwirksamkeit einer Auftragsvergabe in einem Nachprüfungsverfahren ist fristgebunden. Es wird auf die in § 135 Abs. 2 GWB genannten Fristen verwiesen. Nach
§ 135 Abs. 2 S. 2 GWB endet die Frist zur Geltendmachung der Unwirksamkeit 30 Kalendertage nach Veröffentlichung der Bekanntmachung der Auftragsvergabe im Amtsblatt der
Europäischen Union. Nach Ablauf der jeweiligen Frist kann eine Unwirksamkeit nicht mehr festgestellt werden.
VI.5)Date of dispatch of this notice:
22/05/2023
Section VII: Modifications to the contract/concession
VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code
71240000 Architectural, engineering and planning services
VII.1.2)Additional CPV code(s)
71240000 Architectural, engineering and planning services
VII.1.3)Place of performance
NUTS code: DE21F Miesbach
Main site or place of performance:
VII.1.4)Description of the procurement:
VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 15/02/2021
End: 30/06/2022
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)
Total value of the contract/lot/concession: 276 000.00 EUR
VII.2)Information about modifications
VII.2.1)Description of the modifications
Nature and extent of the modifications (with indication of possible earlier changes to the contract):
Mengenmehrung: Aufgebrauchte Stunden im Jahr 2022 somit ist eine Mengenmehrung der Stunden für das Jahr 2023 notwendig,
um abschließenden Arbeiten zu gewährleisten. LÄ03
VII.2.2)Reasons for modification
Need for modification brought about by circumstances which a diligent contracting authority/entity could not foresee (Art. 43(1)(c) of Directive 2014/23/EU, Art. 72(1)(c) of Directive
2014/24/EU, Art. 89(1)(c) of Directive 2014/25/EU)
Description of the circumstances which rendered the modification necessary and explanation of the unforeseen nature of these circumstances:
Das vertragliche Leistungssoll, welches auf Stundenbasis (Aufwand) erstellt wurde, reicht im Rahmen der erforderlichen
Bauleistungen im Zeitraum vom LOS 2: 15.02.21 – 30.12.2022 nicht aus. Die entstanden Verzögerungen im Bauablauf durch
die Verschiebung von IBN Terminen, fehlenden Planunterlagen und Mehrungen im Bauablauf durch die Intensivierung von
Zeitabläufen konnten bei der Ausschreibung nicht mitberücksichtigt werden, wodurch das Soll im Hauptvertrag überschritten
ist. Hierdurch entstehen die Mengenmehrungen in den Stunden bzw. bei den Personalen.
VII.2.3)Increase in price