Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
S3 Weinviertler Schnellstraße, Hollabrunn - Guntersdorf, Neubau
Reference number: 0
II.1.2)Main CPV code
45233100 Construction work for highways, roads - IA39
II.1.3)Type of contract
Works
II.2)Description
II.2.1)Title:
Neubau der S3 Weinviertler Schnellstraße von Hollabrunn - Guntersdorf
II.2.3)Place of performance
NUTS code: AT Österreich
II.2.4)Description of the procurement at the time of conclusion of the
contract:
Neubau der S3 Weinviertler Schnellstraße von Hollabrunn - Guntersdorf
II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 04/06/2018
End: 15/12/2020
In the case of framework agreements, provide justification for any duration exceeding 4 years:
II.2.13)Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds: no
Section V: Award of contract/concession
Title:
Neubau S3 Hollabrunn - Guntersdorf
V.2)Award of contract/concession
V.2.1)Date of conclusion of the contract/concession award decision:
09/05/2018
V.2.2)Information about tenders
The contract/concession has been awarded to a group of economic operators: yes
V.2.3)Name and address of the contractor/concessionaire
Official name: Porr Bau GmbH, Überregionaler Erdbau
Town: Wien
NUTS code: AT Österreich
Country: Austria
The contractor/concessionaire is an SME: no
V.2.3)Name and address of the contractor/concessionaire
Official name: Leyrer + Graf Baugesellschaft m.b.H., Zentrale / Firmenhauptsitz
Town: Gmünd
NUTS code: AT Österreich
Country: Austria
The contractor/concessionaire is an SME: no
V.2.3)Name and address of the contractor/concessionaire
Official name: Bauunternehmung Granit Gesellschaft m.b.H., Zentrale Kalkulation
Town: Graz
NUTS code: AT Österreich
Country: Austria
The contractor/concessionaire is an SME: no
V.2.4)Information on value of the contract/lot/concession (at the time of conclusion
of the contract;excluding VAT)
Total value of the procurement: 55 099 946.89 EUR
Section VII: Modifications to the contract/concession
VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code
45233100 Construction work for highways, roads - IA39
VII.1.2)Additional CPV code(s)
VII.1.3)Place of performance
NUTS code: AT Österreich
Main site or place of performance:
Projektgebiet und St. Pölten
VII.1.4)Description of the procurement:
- Mehrkosten aufgrund zusätzl. angeord. Wirtschaftswege, weiterer Mehrleist. b. div. Wirtschaftsw. u. sonstiger zusätzl. Leistungen i. Zuge d. Gesamtfertigst. sowie d. dadurch
erforderl. Erstreckung d. Bauzeit auf 28.05.2021- Mehrkosten aufgrund außergewöhnlicher Witterung (Niederschläge) im Betrachtungszeitraum Juni 2020 b. 18.12.2020 und daraus
resultierend eventuelle Auswirkungen auf die Leistungsfrist- Forcierungsarbeiten für Verkehrsfreigabe- Maßnahmen COVID-19 Phase 2 (övb-Leitfaden)
VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or
concession
Start: 04/06/2018
End: 15/12/2020
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)
Total value of the contract/lot/concession: 3 744 165.63 EUR
VII.1.7)Name and address of the contractor/concessionaire
Official name: Porr Bau GmbH
Town: Wien
NUTS code: AT Österreich
Country: Austria
The contractor/concessionaire is an SME: no
VII.1.7)Name and address of the contractor/concessionaire
Official name: Leyrer + Graf Baugesellschaft m.b.H.
Town: Gmünd
NUTS code: AT Österreich
Country: Austria
The contractor/concessionaire is an SME: no
VII.1.7)Name and address of the contractor/concessionaire
Official name: Bauunternehmung Granit Gesellschaft m.b.H.
Town: Graz
NUTS code: AT Österreich
Country: Austria
The contractor/concessionaire is an SME: no
VII.2)Information about modifications
VII.2.1)Description of the modifications
Nature and extent of the modifications (with indication of possible earlier changes to the contract):
- Mehrkosten aufgrund zusätzl. angeord. Wirtschaftswege, weiterer Mehrleist. b. div. Wirtschaftsw. u. sonstiger zusätzl. Leistungen i. Zuge d. Gesamtfertigst. sowie d. dadurch
erforderl. Erstreckung d. Bauzeit auf 28.05.2021- Mehrkosten aufgrund außergewöhnlicher Witterung (Niederschläge) im Betrachtungszeitraum Juni 2020 b. 18.12.2020 und daraus
resultierend eventuelle Auswirkungen auf die Leistungsfrist- Forcierungsarbeiten für Verkehrsfreigabe- Maßnahmen COVID-19 Phase 2 (övb-Leitfaden)
VII.2.2)Reasons for modification
Need for additional works, services or supplies by the original contractor/concessionaire (Art. 43(1)(b) of Directive 2014/23/EU, Art. 72(1)(b) of Directive 2014/24/EU, Art. 89(1)(b)
of Directive 2014/25/EU)
Description of the economic or technical reasons and the inconvenience or duplication of cost preventing a change of contractor:
Die gegenständliche Änderung war trotz gebotener Sorgfaltspflicht für den Auftraggeber nicht ersichtlich. Ein Wechsel des Auftragnehmers ist aus technischen und wirtschaftlichen
Gründen nicht möglich, da die gegenständliche Vertragsänderung in einem engen wirtschaftlichen bzw. technischen Zusammenhang mit dem ursprünglichen Auftrag steht. Zudem würde
ein Wechsel des Auftragnehmers für den Auftraggeber zu erheblichen Schwierigkeiten in der Auftragsabwicklung führen, da eine zeitliche Unterbrechung des Auftrages die
termingerechte Realisierung des Projektes gefährden und auch unzählige Schnittstellenprobleme aufwerfen würde. In weiterer Folge wäre der Auftraggeber auch mit beachtlichen
Zusatzkosten aufgrund von Einarbeitungen, Vorbereitungsmaßnahmen, unvermeidbare Parallelbearbeitung bzw. allfälligen Stehzeiten konfrontiert.
VII.2.3)Increase in price
Updated total contract value before the modifications (taking into account possible earlier contract modifications and price adaptions and, in the case of Directive 2014/23/EU,
average inflation in the Member State concerned)
Value excluding VAT: 60 049 674.07 EUR
Total contract value after the modifications
Value excluding VAT: 63 793 839.70 EUR