Regulator Overhauls (Великобритания (Англия, Шотландия, Уэльс) - Тендер #41171253) | ||
| ||
Для перевода текста тендера на нужный язык воспользуйтесь приложением: | ||
Страна: Великобритания (Англия, Шотландия, Уэльс) (другие тендеры и закупки Великобритания (Англия, Шотландия, Уэльс)) Организатор тендера: Northern Gas Networks Limited Номер конкурса: 41171253 Дата публикации: 27-04-2023 Источник тендера: Государственные закупки Уэльса (часть Соединённого Королевства Великобритании и Северной Ирландии) |
||
Title: | Regulator Overhauls |
OCID: | ocds-h6vhtk-02874b |
Published by: | Northern Gas Networks Limited |
Authority ID: | AA20676 |
Publication Date: | 26/04/2023 |
Deadline Date: | |
Deadline Time: | |
Notice Type: | Contract Award Notice |
Has Documents: | No |
Has SPD: | No |
Abstract: |
The Gas Distribution Networks have recently presented their Business Plans to Ofgem for RIIO-2 which is a five-year price control from 2021 - 2026. Ofgem issued their final determinations in December 2020 and NGTN are now in a position where we can plan to deliver the asset upgrades, we have set out in our business plan. This framework agreement is to support NGN in delivering its Regulator Major Overhaul programme of works. The scope will include interventions on assets on our Offtake and PRS sites and the contractor on this framework will need to comply with NGN"s policies and procedures, including the G17 safety policy, as well as the relevant international and national construction and gas industry regulations and standards. The scope of works will include, but not be limited to, the following activities: Mechanical requirements: • Adoption of Work Procedure NGN/PR/MAINT/2301 to cover all decommissioning, recommissioning and overhaul works • Provision of a competent Team Leader to coordinate all works under a Form of Authority (FOA) in accordance with NGN/PR/MAINT/2301 • Undertake decommissioning/isolation activities in accordance with NGN/PR/MAINT/2301 ensuring continuity of supply by leaving at least one stream running onsite • If an axial flow, remove the Regulator from the isolated stream (ONLY REQUIRED ON AXIAL FLOW, NOT REQUIRED ON FIORENTINI"S) • Confirm the stream is adequately supported before regulators are taken out of line • Complete the major overhaul of regulators, control pilots, primary protective devices, reliefs and associated equipment for each site as defined in the NGN/PM/MAINT/2 Part 3 Appendix C. • Reinstall regulator(s). Using new gaskets and nuts/bolts as required (in line with G19 requirements) • Complete all of the above for all regulators within isolated stream • Procure lifting ops/equipment for larger regulators/equipment. This should be done when safe manual handling techniques are no longer adequate. • Undertake recommissioning activities in accordance with manufacturers commissioning instructions • Touch up painting to nuts, bolts and affected paintwork to NGN Standard as required • Provide a full description of completed works on the required technical paperwork within NGN/PM/MAINT/2 Part 3 Appendix C. For the avoidance of doubt all of the above shall be required for each stream on each site Upon arrival on site, the Contractor may deem the following additional activities to be required to make the site complete: • Replacement of any inspirator/restrictor blocks/other elements of the pressure control system (slam-shut bottle regulators L16"s etc) • Any required new pipework/impulse pipework/slam-shut cabinets/ fittings based on condition • Minor civils activities as may be required |
NORTHERN GAS NETWORKS LIMITED
05167070
1100 Century Way Thorpe Park
LEEDS
LS158TU
UK
Contact person: Andrew Christophers
Telephone: +44 7510367358
E-mail: achristophers@northerngas.co.uk
NUTS: UKE42
Internet address(es)
Main address: https://www.northerngasnetworks.co.uk
I.6) Main activity
Production, transport and distribution of gas and heat
Regulator Overhauls
II.1.2) Main CPV code50500000
II.1.3) Type of contractServices
II.1.4) Short descriptionThe Gas Distribution Networks have recently presented their Business Plans to Ofgem for RIIO-2 which is a five-year price control from 2021 - 2026. Ofgem issued their final determinations in December 2020 and NGTN are now in a position where we can plan to deliver the asset upgrades, we have set out in our business plan. This framework agreement is to support NGN in delivering its Regulator Major Overhaul programme of works. The scope will include interventions on assets on our Offtake and PRS sites and the contractor on this framework will need to comply with NGN"s policies and procedures, including the G17 safety policy, as well as the relevant international and national construction and gas industry regulations and standards.
II.1.6) Information about lotsThis contract is divided into lots: No
II.1.7) Total value of the procurementLowest offer: / Highest offer:
NUTS code:
UKC
UKD
UKE
II.2.4) Description of the procurementThe Gas Distribution Networks have recently presented their Business Plans to Ofgem for RIIO-2 which is a five-year price control from 2021 - 2026. Ofgem issued their final determinations in December 2020 and NGTN are now in a position where we can plan to deliver the asset upgrades, we have set out in our business plan. This framework agreement is to support NGN in delivering its Regulator Major Overhaul programme of works. The scope will include interventions on assets on our Offtake and PRS sites and the contractor on this framework will need to comply with NGN"s policies and procedures, including the G17 safety policy, as well as the relevant international and national construction and gas industry regulations and standards.
The scope of works will include, but not be limited to, the following activities:
Mechanical requirements:
• Adoption of Work Procedure NGN/PR/MAINT/2301 to cover all decommissioning, recommissioning and overhaul works
• Provision of a competent Team Leader to coordinate all works under a Form of Authority (FOA) in accordance with NGN/PR/MAINT/2301
• Undertake decommissioning/isolation activities in accordance with NGN/PR/MAINT/2301 ensuring continuity of supply by leaving at least one stream running onsite
• If an axial flow, remove the Regulator from the isolated stream (ONLY REQUIRED ON AXIAL FLOW, NOT REQUIRED ON FIORENTINI"S)
• Confirm the stream is adequately supported before regulators are taken out of line
• Complete the major overhaul of regulators, control pilots, primary protective devices, reliefs and associated equipment for each site as defined in the NGN/PM/MAINT/2 Part 3 Appendix C.
• Reinstall regulator(s). Using new gaskets and nuts/bolts as required (in line with G19 requirements)
• Complete all of the above for all regulators within isolated stream
• Procure lifting ops/equipment for larger regulators/equipment. This should be done when safe manual handling techniques are no longer adequate.
• Undertake recommissioning activities in accordance with manufacturers commissioning instructions
• Touch up painting to nuts, bolts and affected paintwork to NGN Standard as required
• Provide a full description of completed works on the required technical paperwork within NGN/PM/MAINT/2 Part 3 Appendix C.
For the avoidance of doubt all of the above shall be required for each stream on each site
Upon arrival on site, the Contractor may deem the following additional activities to be required to make the site complete:
• Replacement of any inspirator/restrictor blocks/other elements of the pressure control system (slam-shut bottle regulators L16"s etc)
• Any required new pipework/impulse pipework/slam-shut cabinets/ fittings based on condition
• Minor civils activities as may be required
II.2.11) Information about optionsOptions: Yes
Description of options:
Option to extend for three one year periods following conclusion of initial term
II.2.13) Information about European Union fundsThe procurement is related to a project and/or programme financed by European Union funds: No
Negotiated with call for competition
IV.1.8) Information about Government Procurement Agreement (GPA)The procurement is covered by the Government Procurement Agreement: No
Notice number in the OJ S:
2021/S 000-000004
A contract/lot is awarded: Yes
03/04/2023
V.2.2) Information about tendersThe contract has been awarded to a group of economic operators: No
V.2.5) Information about subcontractingNorthern Gas Networks
Leeds
UK
25/04/2023
Information added to the notice since publication.
Additional information added to the notice since it"s publication.No further information has been uploaded. |
Main Contact: | achristophers@northerngas.co.uk |
Admin Contact: | N/a |
Technical Contact: | N/a |
Other Contact: | N/a |
ID | Title | Parent Category |
---|---|---|
50500000 | Repair and maintenance services for pumps, valves, taps and metal containers and machinery | Repair and maintenance services |
ID | Description |
---|---|
100 | UK - All |
The buyer has restricted the alert for this notice to suppliers based in the following regions.