Syria Electricity Emergency Project (Сирия - Тендер #66898881) | ||
| ||
| Для перевода текста тендера на нужный язык воспользуйтесь приложением: | ||
Страна: Сирия (другие тендеры и закупки Сирия) Организатор тендера: The World Bank Номер конкурса: 66898881 Дата публикации: 11-09-2025 Источник тендера: Тендеры всемирного банка |
||
P511407
Syria Electricity Emergency Project
Syrian Arab Republic
OP00377821
General Procurement Notice
Published
N/A
English
Sep 10, 2025
The Public Establishment for Transmission and Distribution of Electricity
Homam Harba
Damascus- Syria
Syrian Arab Republic
Syrian Arab Republic
00963944611972
http://www.tde.gov.sy
GENERAL PROCUREMENT NOTICE
Syrian Arab Republic
Syria Electricity Emergency Project
Energy Sector
GENERAL PROCUREMENT NOTICE
/Grant No. IDA-E4880
Project ID No. P511407
The Syrian Arab Republic has applied for grant financing in the amount of US$ 146 million equivalent from the World Bank toward the cost of the Syria Electricity Emergency Project, and it intends to apply part of the proceeds to payments for goods, works, non-consulting services and consulting services to be procured under this project. This project will be financed by the International Development Association (IDA)
The project will include the following components
Component 1: Rehabilitation of Damaged High-Voltage Transmission Lines (estimated cost of US$25 million): Component 1 will focus on rehabilitating the damaged parts of the two critical 400 kV high-voltage interconnector transmission lines in Syria, restoring Syria’s regional connectivity to Jordan and Türkiye, thus enabling the import of around 600 MW combined from Jordan and Türkiye, which will benefit the entire electricity network across Syria. The length of the two lines inside Syria are approximately 88 km for the Syria-Jordan line and 55 km for the Syria- Türkiye line, The restoration of these lines is essential for enabling electricity imports into Syria and improving the stability of PETDE’s electricity network. It is expected that about 10 damaged 400 kV steel lattice towers, approximately 950 km (2000 tons) of overhead conductors (550/70 sq mm), 160 km of OPGW, insulators and other accessories.
The following procurement packages are envisaged under component 1:
|
|
Category |
Market Approach |
Procurement Method |
Date of Specific Procurement Notice |
|
Rehabilitation of the two 400 kV high-voltage interconnector transmission lines to Turkey and Jordan (supply and installation of damaged towers, civil works, replacement of conductors, insulators, optical ground wires, and other required equipment and spare parts) |
Works |
Open - International |
Request For Bids (RFB)- Plant (Supply & Install) without prequalification |
Oct-25 |
|
Supply of 2 Lines cleaning vehicles and 2 Lines Fault detection vehicles |
Goods |
Open - International |
RFB- Single Stage Two Envelopes |
Jun-26 |
Component 2: Rehabilitation of Damaged High-Voltage Substations (estimated cost of US$107 million): Component 2 focuses on rehabilitating damaged, critical high-voltage transformer substations and providing necessary spare parts and maintenance equipment. It is anticipated that eight substations will be rehabilitated under this Component; thus, restoring approximately 900 mega volt-amperes (MVA) 400/230 kV, 1125 MVA 230/66 kV, and 510 MVA 66/20 kV of transformation capacity back to PETDE’s network.
The following procurement packages are envisaged under component 2:
|
|
Category |
Market Approach |
Procurement Method |
Date of Specific Procurement Notice |
|
Design, Supply and Installation of high voltage transformer substations (total number of transformers as follows: 3x300 (900) MVA 400/230 kV, 9x125 (1125) MVA 230/66 kV and 17x30 (510) MVA 66/20 kV of combined transformation capacity), including the Supply of necessary spare parts |
Works |
Open - International |
Request For Bids (RFB)- Plant (Design, Supply & Install) without prequalification |
Oct-25 |
Component 3: Technical Assistance for Electricity Sector Development and Institutional Capacity Building (estimated cost of US$5 million): Component 3 will provide Technical Assistance (TA) to (i) inform key electricity sector strategies, policy and regulatory reforms, and investment plans for medium to long term sustainability; and (ii) support the electricity sector institutional capacity to implement these strategies and reforms.
The following procurement packages are envisaged under component 3:
|
|
Category |
Market Approach |
Procurement Method |
Date of Specific Procurement Notice |
|
Providing of Power system planning software Licenses and relevant capacity building and Training. |
Goods |
Open - International |
RFB- Single Stage Two Envelopes |
Dec-2026 |
|
Dam safety Assessment |
Consulting Services |
Open - International |
Quality and Cost Based Selection (QCBS) |
Dec-2026 |
|
Renewable Energy Assessment |
Consulting Services |
Open - International |
QCBS |
Aug-2026 |
|
Market Reform and Unbundling Analysis |
Consulting Services |
Open - International |
QCBS |
Dec-2026 |
|
E&S Capacity Building |
Consulting Services |
Open - International |
QCBS |
Jun-2026 |
|
Enabling Private Sector Participation in Electricity market |
Consulting Services |
Open - International |
QCBS |
Aug-2026 |
|
Cost of Service Reform and Social Safet Net Design |
Consulting Services |
Open - International |
QCBS |
Oct-2026 |
Component 4: Project Implementation Support (estimated cost of US$9 million): This component will finance the Owner’s Engineer (OE), who will be hired by PETDE. The OE will be responsible for technical supervision of the main contracts under Components 1 and 2 of the Project. This includes contract management, monitoring contractors’ compliance with environment and social (E&S) requirements, supervising sites and ensuring quality control, addressing climate resilience and adaptation needs in all designs, managing financial aspects and reporting, and reviewing and approving payment certificates, and other aspects of contracts related to Components 1 and 2. The component will also finance consulting services (Individuals and Firms) to support the implementation of the project.
The following procurement packages are envisaged under component 4:
|
|
Category |
Market Approach |
Procurement Method |
Date of Specific Procurement Notice |
|
Selection of Owner Engineer for the supervision Stage (Time Based Contract) |
Consulting Services |
Open - International |
QCBS |
Sep-25 |
Procurement of contracts financed by the World Bank will be conducted through the procedures as specified in the World Bank’s Procurement Regulations for IPF Borrowers dated February 2025 (Procurement Regulations), and is open to all eligible firms and individuals as defined in the Procurement Regulations. After project negotiations, the World Bank shall arrange the publication on its external website of the agreed initial procurement plan and all subsequent updates once it has provided a no objection.
Specific procurement notices for contracts subject to open international competitive procurement will be announced, as they become available on the World Bank’s external website and on the following free access http://www.tde.gov.sy
Interested eligible firms and individuals who would wish to be considered for the provision of goods, works, non-consulting services and consulting services for the above mentioned project, or those requiring additional information, should contact the Borrower at the address below:
Public Establishment for Transmission and Distribution of Electricity
General Director of PETDE :Eng. Khaled Abu Di
Post Address: Syrian Arab Republic – Damascus – Mezzeh – 17 Nissan Street - Opposite Carlton Hotel
Telephone Numbet: +963 11 2135113 / 36
FAX Number: :+963 11 2144435
Email address: Infoseep@tde.gov.sy
Web site address: http://www.tde.gov.sy