Reference Number
|
12058763
|
|
Procuring Entity
|
BARANGAY SALVACION, MALILIPOT, ALBAY
|
|
Title
|
Construction of Water System
|
|
Area of Delivery
|
Albay
|
Printable Version
|
|
Solicitation Number:
|
salvacion 2025-01
|
|
Trade Agreement:
|
Implementing Rules and Regulations
|
|
Procurement Mode:
|
Public Bidding
|
|
Classification:
|
Civil Works
|
|
Category:
|
Construction Projects
|
|
Approved Budget for the Contract:
|
PHP 574,331.51
|
|
Contract Duration:
|
29 Day/s
|
|
Client Agency:
|
|
|
|
Contact Person:
|
Restie Buena
Brgy Captain
Brgy Salvacion
Malilipot
Albay
Philippines 4510
63-052-583266 Ext.123
barangaysalvacion@gmail.com
|
|
Status
|
Active
|
|
Associated Components
|
Order
|
|
Bid Supplements
|
0
|
|
Document Request List
|
0
|
|
Date Published
|
17/07/2025
|
|
Last Updated / Time
|
17/07/2025 12:00 AM
|
|
Closing Date / Time
|
24/07/2025 9:00 AM
|
|
Description
|
Invitation to BID
The Barangay Salvacion, Malilipot, Albay through the Bids and Awards Committee BAC invites suppliers to bid
the hereunder:
Name of the Contract: Construction of Water System
Location: Barangay Salvacion, Malilipot, Albay
Approved Budget for the Contract: 574,331.51
Please quote your lowest price for the item listed below:
1 Lot Supply and Delivery of Labor, Materials for the Construction of Solar Street Lights
Item I - Structure Excavation
Item II - Pipe Trench Excavation
Item III - Reinforced Concrete Works
Item IV - Pipe Laying
Item V - Fill and Backfill
Item VI - Hauling of Materials
Item VII - Project Signage
Prospective bidders should have experience in undertaking similar contract within the last two (2) years with an amount at least 50% of the proposed
contract for bidding. The BAC will use non-discretionary pass/fail criteria in the Eligibility Check/Screening as well as Preliminary of Examination of
bids. The BAC of Barangay Salvacion, Malilipot, Albay will conduct Post-qualification of the lowest calculated bids.
All Particular relative to the eligibility statement and screening, bid security, performance bid, pre-bidding conference, evaluation of bids,
post-qualification and award contract shall governed by the pertinent provision of R.A. 9184 and its Implementing Rules and Regulation (IRR).
Activities Date and Time
1. Advertisement: July 17-24, 2025
2. Issuance of Bid Documents: July 17-24, 2025
3. Deadline of Submission: July 24, 2025; 9:00A.M.
4. Bid Opening: July 24, 2025; 9:30 A.M. at Barangay Hall of Barangay Salvacion, Malilipot, Albay
The BAC of Barangay Salvacion, Malilipot, Albay will issue to the prospective bidders bid forms upon their submission of Letter of Intent (LOI) and upon
their payment of non-refundable amount of Five Hundred Pesos, (500.00) to the Barangay Treasurer of Barangay Salvacion, Malilipot, Albay
The Barangay Salvacion, Malilipot, Albay reserves the right to reject any all bids, waive minor defect therein and accept the offer of most advantageous to
the government.
The Barangay Salvacion, Malilipot, Albay, assumes no responsibility whatsoever to compensate of indemnify the bidders expenses in the preparation of the
bid.
APPROVED BY:
RESTIE BUENA
PUNONG BARANGAY
SALVACION, MALILIPOT, ALBAY
|
|
|
|
Line Items
|
|
Item No.
|
Product/Service Name
|
Description
|
Quantity
|
UOM
|
Budget (PHP)
|
|
1
|
Construction of Water System
|
Construction Projects
|
1
|
Lump Sum
|
574,331.51
|
|
|
|
|
|
|
|
Created by
|
Restie Buena
|
|
Date Created
|
22/05/2025
|
|
|
|
|