Reference Number
|
11827131
|
|
Procuring Entity
|
BARANGAY SAN LORENZO - IGUIG CAGAYAN
|
|
Title
|
CONTINUATION OF EVACUATION CENTER, Construction Projects, BARANGAY SAN LORENZO IGUIG CAGAYAN
|
|
Area of Delivery
|
Cagayan
|
Printable Version
|
|
Solicitation Number:
|
2025-02-001
|
|
Trade Agreement:
|
Implementing Rules and Regulations
|
|
Procurement Mode:
|
Public Bidding
|
|
Classification:
|
Civil Works
|
|
Category:
|
Construction Projects
|
|
Approved Budget for the Contract:
|
PHP 326,158.00
|
|
Contract Duration:
|
45 Day/s
|
|
Client Agency:
|
|
|
|
Contact Person:
|
MANOLO MATEO
Punong Barangay
Barangay San Lorenzo,Iguig,Cagayan
Iguig
Cagayan
Philippines 3504
63-917-5034068
barangayiguig23@gmail.com
|
|
Status
|
Active
|
|
Associated Components
|
Order
|
|
Bid Supplements
|
0
|
|
Document Request List
|
0
|
|
Date Published
|
18/03/2025
|
|
Last Updated / Time
|
18/03/2025 12:00 AM
|
|
Closing Date / Time
|
27/03/2025 8:30 AM
|
|
Description
|
Project Name: Continuation of Evacuation Center
Project Location: San Lorenzo, Iguig, Cagayan
"ITEM
NO." DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST GRAND TOTAL
MATERIAL MATERIAL LABOR
1.00 Cement Plaster Finish sq.m 78.72
Cement bags 12.00 x 260.00 = 3,120.00 936.00 = 4,056.00
Sand cu.m 0.945 x 600.00 = 567.00 170.10 = 737.10
Sub-total 4,793.10
Unit Cost= Php 4,793.10 / 78.72 sq.m = 60.89 / sq.m
Total Item Cost= Php 60.89 x 78.72 sq.m = 4,793.10
2.00 Floor Tiles sq.m 108.00
Tile Grout bags 10.00 x 250.00 = 2,500.00 750.00 = 3,250.00
P. Cement kgs 48.60 x 260.00 = 12,636.00 4212.00 = 16,848.00
Adhesive bags 12.00 x 250.00 = 3,000.00 900.00 = 3,900.00
Tiles 40x40 pcs 702.00 x 70.00 = 49,140.00 17,016.00 = 66,156.00
Sub-Total = 90,154.00
Unit Cost= Php 90,154.00 / 108.00 sq.m = 834.76 / sq.m
Total Item Cost= Php 834.76 x 108.00 sq.m = 90.154.00
3.00 Fenestration Works
a. Doors
2.1x 0.80 Door set 3.00 x 8,500 = 25,500.00 7,650.00 = 33,150.00
b.Window
1.5x 1.5 Window set 6.00 x 5,400.00 = 32,400.00 9,720.00 = 42,120.00
0.5x 1.5 Window set 2.00 x 5,300.00 = 10,600.00 3,180.00 = 13,780.00
c.Hand Rail
G.I Tubular I.s 1.00 x 22,680.00 = 22,680.00 6,804.00 = 29,484.00
Sub-Total = 118,534.00
4.00 Carpentry Works sq.m 108.00
Metal Furring( Interior & Exterior) sq.m 108.00
Furring Channel( Spaced @ 0.6m) pc 46.00 x 135.00 = 6,210.00 2,430.00 = 8,640.00
Carrying Channel (Spaced @ 1.2 m) pc 28.00 x 145.00 = 4,060.00 1,767.00 = 5,827.00
Wall Angle pc 35.00 x 91.00 = 3,185.00 955.50 = 4,140.50
W Clip pc 254.00 x 10.00 = 2,540.00 762.00 = 3,302.00
Suspension Clip & Rod Joiner pc 30.00 x 15.00 = 450.00 585.00 = 1,035.00
Hanger Rod # 8 Im 12.00 x 85.00 = 1,020.00 3,315.00 = 4,335.00
Blind Rivels pc 533.00 x 3.00 = 1,599.00 4,797.00 = 6,396.00
Concrete Nail (1") kg 2.00 x 140.00 = 280.00 84.00 = 364.00
Ceiling Boards ( Interior) sq.m 108.00 =
Shera Board 1/4"x 4"x8" pc 37.00 x 480.00 = 17,760.00 4,717.50 = 22,477.50
Sub-Total = 56,517.00
Unit Cost = Php 56,517.00 / 108.00 sq.m = 523.31 / sq.m
Total Item Cost = Php 667.47 x 108.00 sq.m = 56,517.00
I.DIRECT COST 269,998.10
II.INDIRECT COST 40,499.72
III. VAT 15,524.89
IV. PROJECT COST 326,022.71
Say 326,158.00
|
|
|
|
|
|
|
|
|
Created by
|
MANOLO MATEO
|
|
Date Created
|
28/02/2025
|
|
|
|
|