C2810 Wastewater Flowmeter Installation Programme (Новая Зеландия - Тендер #61820224) | ||
| ||
| Для перевода текста тендера на нужный язык воспользуйтесь приложением: | ||
Страна: Новая Зеландия (другие тендеры и закупки Новая Зеландия) Организатор тендера: New Zealand Government Electronic Tenders Service Номер конкурса: 61820224 Дата публикации: 25-02-2025 Источник тендера: Государственные закупки Новой Зеландии |
||
| RFx ID : | 31036557 |
| Tender Name : | C2810 Wastewater Flowmeter Installation Programme |
| Reference # : | C2810 |
| Open Date : | Monday, 10 February 2025 3:00 PM (Pacific/Auckland UTC+13:00) |
| Close Date : | Friday, 28 February 2025 12:00 PM (Pacific/Auckland UTC+13:00) |
| Department/Business Unit : | Infrastructure - 3 Waters |
| Tender Type : | Request for Tenders (RFT) |
| Tender Coverage : | Sole Agency [?] |
| Categories : |
|
| Regions: |
|
| Exemption Reason : | None |
| Required Pre-qualifications : | None |
| Contact : |
Patricia van der Westhuizen patriciaw@napier.govt.nz |
| Alternate Physical Delivery Address : | |
| Alternate Physical Fax Number : |
Napier City Council are looking for a contractor to install a programme of flow meters at wastewater pump stations across the city to provide data to inform current use and modelling for the
future.
What we need?
- A general concept design has been completed for buried flowmeters; however, each site has its own intricacies and an element of onsite design for installation and connectivity is required.
Following installation, as-built mark-ups are required to be submitted for engineering approval.
- A prioritised list of pump station locations and co-ordinates is attached to this Notice. The Contractor will work through the installation completing as many as possible to the Maximum Fee
using the agreed Schedule of Rates.
- To mitigate the flow meter lead in times (6 – 8 weeks) the Principal will purchase a supply of flow meters in advance and make them available to the Contractor to complete the works and
reinstatement within a timely manner.
- The electrical work and integration to SCADA is not included in the scope of this procurement.