Страна: Индия (другие тендеры и закупки Индия) Организатор тендера: The World Bank Номер конкурса: 66801377 Дата публикации: 08-09-2025 Источник тендера: Тендеры всемирного банка |
||
P165129
Integrated Project for Source Sustainability and Climate Resilient Rain-fed Agriculture in Himachal
India
OP00377106
Invitation for Bids
Published
IN-DPO, KANGRA-494431-CW-RFQ
Request for Quotations
English
Sep 17, 2025 11:00
Sep 06, 2025
District Project Office, Kangra, Himachal Pradesh Forestry Department
Narender Singh
District Kangra Himachal Pradesh
India
India
7018327567
REQUEST FOR QUOTATIONS
Procurement of Works under RFQ/Shopping Procedures
Procurement Notice
((Single-Envelope with Offline Procurement Bidding Process)
Project: INTEGRATED DEVELOPMENT PROJECT, (IDP)
KANGRA AT DHARAMSHALA
Contract title: Irrigation Chahanel Kuhal, CC Check Barriers & Direct Irrigation
RFQ No. ________ STEP Ref . No. IN-DPO- Kangra- 494431, 506519 & 50626 -CW-RFQ
Date:-
Applicable Procurement Guidelines/Regulations Dated: APRIL, 2018.
1. Government of India has received/has applied for/intends to apply for financing from the World Bank towards the cost of the Project and intends to apply part of the proceeds of this credit to eligible payments under the contract for which this request for quotations is issued. The District Project Officer, Integrated Development Project, Kangra at Dharamshala, invites quotations offline from eligible bidders for construction of the following works.
|
Job No. |
Brief Description of the Works |
Qty. in Rmt |
Approximate value of Works (Rs.) |
Period of Completion |
|
NB-1 Sect. Str/ 2025-26 |
C/O Cement Conc.Chanel/ Kuhal at Sihund from Amlal kuhal near Sh. Bhagi Ram to Sh. Chaina Ram land & Other landholder ward No--3 in GP. Sihund under APO- Nagrota-Bagwan |
297 |
482500 |
90 Days |
|
NB-2 Sect. Str/ 2025-26 |
C/O Cement Conc.Chanel/ Kuhal at Jandrah from Soler kuhal near Smt. Anita Kumari to Sh.Dhanu Ram land & Other landholder ward No--3 in GP. Jandrah under APO- Nagrota-Bagwan |
297 |
496200 |
90 Days |
|
NB-3 Sect. Str/ 2025-26 |
C/O Cement Conc.Chanel/ Kuhal at Baldher from Lahar kuhal to Sh. Rakesh Kumar land & Other landholder ward No--3 in GP. Baldher under APO- Nagrota-Bagwan |
295 |
479200 |
90 Days |
|
NB-4 Sect. Str/ 2025-26 |
C/O Cement Conc.Chanel/ Kuhal at Rounkhar from main kuhal near Sh. Raj Kumar to Palyalu land & Other landholder ward No--3 in GP. Rounkhar under APO- Nagrota-Bagwan |
271 |
478732 |
90 Days |
|
NB-5 Sect. Str/ 2025-26 |
C/O Cement Conc.Chanel/ Kuhal at Thana Khas near Sh. Vijay Kumar to Sh. Munshi Ram land & Other landholder ward No-2 in GP. Serathana under APO- Nagrota-Bagwan |
267 |
485600 |
90 Days |
|
PR-1/ Sect. Str/ 2025-26 |
C/O Cement Concreate Chanel/Kuhal(Secondry Scheme) at Chhattar from main head near Sh.Bakshi Ram to Sh.Swaran Dass land & Other landholders ward no.-1 in GP-Andreta in APO- Panchru khi |
265 |
475500 |
90 Days |
|
PR-2/ Sect. Str/ 2025-26 |
C/O Cement Concreate Chanel/Kuhal(Secondry Scheme) at Kharmanker from Dohri Kuhal near Sh. Sudharshan Sharma land to Sh. Raj Mal land ward no.-4 in GP- Jaind under APO- Panchrukhi |
255 |
466200 |
90 Days |
|
PR-3/ Sect. Str/ 2025-26 |
C/O Cement Concreate Chanel/Kuhal(Secondry Scheme) at Ladoh Gaghroon kuhal near Sh.Ashish Kumar land to Sh. Swroop Chand Sharma & other landholers land ward no.-2 in GP-Ladoh under APO- Panchrukhi |
272 |
482600 |
90 Days |
|
PR-4/ Sect. Str/ 2025-26 |
C/O Cement Concreate Chanel/Kuhal(Secondry Scheme) at Gurehar from kuhal near Sh. Swaroop Chand land to Sh. Surender Ramba & other landholers land ward no.-1 in GP- Saliana under APO- Panchrukhi |
296 |
472600 |
90 Days |
|
PR-5/ Sect. Str/ 2025-26 |
C/O Cement Concreate Chanel/Kuhal(Secondry Scheme) at Tatehal Ghodeyan de kuhal from intake Ladoh nallah to Sh.Amit Kumar Rana land & Other landholders ward no.-2 in GP-Tatehal in APO- Panchru khi |
265 |
484300 |
90 Days |
|
PR-6/ Sect. Str/ 2025-26 |
C/O Cement Concreate Chanel/Kuhal(Secondry Scheme) at Tatehal from Sh.Vishavjeet land to Sh. Suresh Kumar land & other landholders ward no.-2 in GP-tatehal under APO- Panchrukhi |
265 |
470200 |
90 Days |
|
PR-7/ Sect. Str/ 2025-26 |
C/O Cement Concreate Chanel/Kuhal(Secondry Scheme) at Dharamdai Khad from Majhenu main head weir to Sh. Om Vyas land & Other landholders ward no.-7 in GP-Gadiyara-I in APO- Panchrukhi |
275 |
478200 |
90 Days |
|
DR-1/ Sect. Str/ 2025-26 |
C/o. Cement Concrete Channel/Kuhal at Bag Tipperi Kuhal to Sh. Bakil Singh land & other landholder ward No-1 in GP . Tipperi in APO –Dehra |
273 |
483800 |
90 Days |
|
DR-2/ Sect. Str/ 2025-26 |
C/o. Cement Concrete Channel/Kuhal at Tipperi Nichla Gharat to Sh. Ashok Kumar, Sh. Birbal Singh land & other landholder ward No-3 in GP .Tipperi under APO- Dehra |
350 |
480000 |
90 Days |
|
DR-3/ Sect. Str/ 2025-26 |
C/o. Cement Concrete Channel/Kuhal at Gurenward from landholder Smt.Asha Devi land to Ram Chander land & other landholder ward No-2 in GP . Gurenward under APO -Dehra |
270 |
478538 |
90 Days |
|
DR-4/ Sect. Str/ 2025-26 |
C/o. Cement Concrete Channel/Kuhal ( Secondry Scheme)at Gurnward from main Kuhal to Sh. Kartar Singh & other landholder ward No -5 in GP. Gurenward in APO- Dehra |
300 |
486300 |
90 Days |
|
DR-5/ Sect. Str/ 2025-26 |
C/o. Cement Concrete Channel/Kuhal at Gurewad from Sh. Jarnail Singh land to Tarkhan Basti land & other landholder ward No-5 in GP . Gurenwad under APO- Dehra |
292 |
472700 |
90 Days |
|
DR-6/ Sect. Str/ 2025-26 |
C/o. Cement Concrete Channel/Kuhal at Gurewad from Sh. Balwant Singh land to Sh. Sukh Dev land & other landholder ward No-5 in GP . Gurenwad under APO- Dehra |
277 |
472400 |
90 Days |
|
BN-1/ Sect. Str/ 2025-26 |
RCC Chamber structure & HDPE pipe line at Niggha nallah near Sh. Man Chand & other land holder ward no. 5 in GP Baragran under APO Baijnath |
435 |
136900 |
90 Days |
|
BN-2/ Sect. Str/ 2025-26 |
RCC Chamber structure & HDPE pipe line at Kolang nallah near Sh. Raj Kumar & other land holder wrad no. 1 in GP Baragran under APO Baijnath |
460 |
143000 |
90 Days |
|
BN-3/ Sect. Str/ 2025-26 |
RCC Chamber structure & HDPE pipe line at Kardhar nallah near Sh. Subash Chand & other land holder wrad no. 5 in GP Baragran under APO Baijnath |
690 |
205195 |
90 Days |
|
BN-4/ Sect. Str/ 2025-26 |
RCC Chamber structure & HDPE pipe line at Cherna to Bardhar from Cherna nallah to other land holder wrad no. 3 in GP Swar under APO Baijnath |
1470 |
398300 |
90 Days |
|
BN-5/ Sect. Str/ 2025-26 |
RCC Chamber structure & HDPE pipe line at Dharman Nallah near Joginder Singh and other land holder wrad no. 5 in GP Dharman under APO Baijnath |
925 |
265700 |
90 Days |
|
DR-27/ DLT / 2025-26 |
Cement Concreate Check barrier (SWC) at Tippri nallah-I near Ward No-1 in GP- Tippri in APO- Dehra under APO- Dehra |
20.05 |
168800 |
90 Days |
|
DR-28/ DLT / 2025-26 |
Cement Concreate Check barrier (SWC) at Tippri tributaries of Bagh nallah-II near Ward No-3 in GP- Tippri under APO- Dehra |
16.63 |
140600 |
90 Days |
|
DR-29/ DLT / 2025-26 |
Cement Concreate Check barrier (SWC) at Ghartu nallah-I in GP- Sawana under APO- Dehra |
19.71 |
166300 |
90 Days |
|
DR-30/ DLT / 2025-26 |
Cement Concreate Check barrier (SWC) at Sawana nallah-II near Ward No-3 in GP- Sawana under APO- Dehra |
16.47 |
138900 |
90 Days |
|
DR-31/ DLT / 2025-26 |
Cement Concreate Check barrier (SWC) at Ujay nallah-I near Ward No-3 in GP- Ujay-Khas under APO- Dehra |
19.96 |
168400 |
90 Days |
|
DR-32/ DLT / 2025-26 |
Cement Concreate Check barrier (SWC) at Tippri from Bagh nallah-III near Ward No-3 in GP- Tippri - under APO- Dehra |
19.8 |
167100 |
90 Days |
|
DR-33/ DLT / 2025-26 |
Cement Concreate Check barrier (SWC) at Ujay nallah- near Ward No-3 in GP-Ujay-Khas under APO- Dehra |
16.55 |
139600 |
90 Days |
|
DR-34/ DLT / 2025-26 |
Cement Concreate Check barrier (SWC) at Tyambal tributaries of Amb nallah-I in G P- Tyambal under APO- Dehra |
19.44 |
163400 |
90 Days |
2. This Procurement notice includes the following documents[1] to facilitate preparation and submission of quotations, criteria for qualification, evaluation, and for award of contract; and relevant forms to be filled by the bidders. Implementing Agency has not issued a separate RFQ document for this works/purchase. The Procurement notice including the various documents and forms to be filled etc.
i. Layout Drawings of the works;
ii. Structural Details;
iii. Detailed Bill of Quantities, with estimated rates and prices;
iv. Technical Specifications;
v. Instructions to Bidders;
vi. Qualification Information;
vii. Format for Submission of Quotation;
viii. Criteria for Evaluation and Award of Contract;
ix. Relevant Forms; and
x. Draft Contract Agreement format which will be used for finalizing the agreement for this Contract.
3. Quotations, both Technical Part and Financial Part shall be submitted offline on 17.09.2025 or before 11.00 A.M. Any quotation or modifications to quotation received after last date of quotation submission will not be considered. The ‘Technical & Financial Part’ of the Quotations will be opened offline on 17.09.2025 at 12.00 Noon. .
|
Description: As mentioned in Page No. 1 |
Date: 02.09.2025 |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Date of publication: |
02.09.2025 |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
EMD:
|
Rs. 10000/ - ( Rs. Ten Thousand only of each job Through FDR/NSC a Nationalized Bank, pledged in favour of DPO IDP KANGRA AT DHARAMSHALA HP payable at DHARAMSHALA.. The tender document is non-transferable. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Bid Submission Start Date |
02.09.2025 |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Last Date for Submission of Bid |
17.09.2025 at 11:00 AM |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Last Date of Physical submission of EMD/ cost of tender & technical bids |
17.09.2025 at 11:00 AM |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Date of opening of the Technical Bids |
17.09.2025 at 12:00 Noon |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Date of opening of Financial Bids |
17.09.2025 at 2:00 PM |
6. If the implementing agency’s office happens to be closed on the date of opening of the Quotations as specified, the ‘Technical Part’ of the Quotations will be opened on the next working day at the same time. The Financial Parts of the Quotations shall remain unopened, until the subsequent opening, following the evaluation of the Technical Parts of the Quotations.
7. Other details can be seen in the RFQ document. The implementing agency shall not be held liable for any delays which are beyond its control. A Bidder requiring any clarification of the RFQ document may notify the Implementing agency offline or may visit the office of the implementing agency at the address given below.
8. The standard quotation/bid form W-5(Schedule of Quantity) alongwith instructions to bidders (Quotation Notice) can be obtained/ procured by the bidders for Rs. 100/- per job or through e-challan to District Project Officer, Integrated Development Project, Kangra at Dharamshala D.D. Code 985 Treasury Code : KNG00 in the revenue Head 0070-60-800-17 Procurement of Tender Fee.
Name: Narender Singh, HPFS
Address: District Project Officer,
Integrated Development Project,
Kangra at Dharamshala. H.P
Telephone No:-01892-223098