AB-2026-02590 - REQUEST FOR PROPOSALS (RFP) FOR CONSTRUCTION MANAGEMENT SERVICES FOR VARIOUS – ALBERTA INNOVATES FACILITIES – Fume Hood Replacement, Laboratory Renewal and Base Building Upgrade - Phase 2 (Calgary Research Park) (Канада - Тендер #71655450) | ||
| ||
| Для перевода текста тендера на нужный язык воспользуйтесь приложением: | ||
Страна: Канада (другие тендеры и закупки Канада) Организатор тендера: www.merx.com Номер конкурса: 71655450 Дата публикации: 02-04-2026 Источник тендера: www.merx.com |
||
Construction management services are required for a multi-facility renewal program involving fume hood replacement, laboratory renewal, and base building upgrades at research facilities.
00004977640
Issuing OrganizationAlberta Infrastructure
Solicitation TypeRFP - Request for Proposal (Formal)
Solicitation NumberAB-2026-02590
TitleREQUEST FOR PROPOSALS (RFP) FOR CONSTRUCTION MANAGEMENT SERVICES FOR VARIOUS – ALBERTA INNOVATES FACILITIES – Fume Hood Replacement, Laboratory Renewal and Base Building Upgrade - Phase 2 (Calgary Research Park)
Source IDSCRIBE
Alberta
Purchase TypeNot Stated
2026/04/01 07:32:00 AM EDT
Closing Date2026/04/21 04:00:00 PM EDT
Mischa Maree
mischa.maree@gov.ab.ca
The intent of this Request for Proposals (“RFP”) is to solicit and receive formal offers from prospective Proponents for the provision of construction management services for the VARIOUS -
ALBERTA INNOVATES FACILITIES - Fume Hood Replacement, Laboratory Renewal and Base Building Upgrades – Phase 2 (Calgary Research Park) (“Project”).
Alberta Infrastructure, on behalf of Alberta Innovates and InnoTech Alberta, is undertaking a multi-facility renewal program to support upgrades across three research facilities in Alberta. As
part of this initiative, the Calgary Research Centre (CRC) has been identified as the first site to proceed into the design phase.
The Calgary Research Centre, located at 3608 – 33 Street NW between the University of Calgary’s main campus and the Brentwood C‑Train Station, was constructed in 2000 and consists of two
storeys. The building accommodates office areas on the south side and a series of research laboratories on the north side.
The services of the Construction Manager will be required for the full project life cycle, from pre-design through to post-occupancy evaluation. Given that multiple construction projects may be
undertaken concurrently across the facility, the Construction Manager shall coordinate design development, construction activities, and project phasing to ensure continued site access,
decanting and relocation processes (as required), and minimize disruption to ongoing facility operations. The Construction Manager shall sequence the work packages in a manner that allows
Alberta Innovates to maintain ongoing research operations, protect revenue-generating activities, and minimize disruption to critical equipment, laboratories, and scientific workflows.
Information/Pre-bid Meeting**Mandatory
Thu•Apr 9, 2026•1:00 pm (MT)