AB-2026-02260 - RFP26-1528 Airport Transit Connection (East Leg) – Blue Line LRT to Calgary Airport (Канада - Тендер #71402628) | ||
| ||
| Для перевода текста тендера на нужный язык воспользуйтесь приложением: | ||
Страна: Канада (другие тендеры и закупки Канада) Организатор тендера: www.merx.com Номер конкурса: 71402628 Дата публикации: 19-03-2026 Источник тендера: www.merx.com |
||
A qualified firm is sought to provide functional planning, preliminary and detailed design engineering and architectural services for the Airport Transit Connection project linking the Blue Line LRT to Calgary Airport.
00004957163
Issuing OrganizationThe City of Calgary
Solicitation TypeRFP - Request for Proposal (Formal)
Solicitation NumberAB-2026-02260
TitleRFP26-1528 Airport Transit Connection (East Leg) – Blue Line LRT to Calgary Airport
Source IDSCRIBE
Alberta
Purchase TypeNot Stated
2026/03/19 03:13:00 PM EDT
Closing Date2026/04/22 06:00:00 PM EDT
City of Calgary
403-268-5540
This RFP is open to all interested parties. The City of Calgary requires the services of a qualified firm to provide functional planning, preliminary and detailed design engineering and
architectural services for the Airport Transit Connection (East Leg) – Blue Line LRT to Calgary Airport project.
This project anticipates the project phases and requirements as described below: Phase 1 – Assessment of the connection to the Blue Line LRT System; Phase 2 – Train technology re-assessment
and recommendation; Phase 3 – Re-assessment of rail access to a maintenance and storage facility; Phase 4 – Maintenance and storage facility functional planning study; Phase 5 – Updates
to all the Airport Trail functional planning studies to reflect the proposed Airport Transit Line; Phase 6 – Airport Transit Line operation in Airport Tunnel; Phase 7 – Airport terminal
station jurisdictional scan and scoping studies; Phase 8 – Complete preliminary design for all the above-mentioned work phases; Phase 9 – Project delivery model assessment (by The City);
Phase 10 – Owner’s engineer’s role in case of a P3 project delivery method; Phase 11 – Complete the detailed design based on the preliminary design; Phase 12 – Provide construction
contract administration services (currently unfunded); and Phase 13 – Post construction administration services (currently unfunded).
This procurement process is not intended to create, and, will not create, a formal, legally binding bidding process. It will instead be governed by the law applicable to direct commercial
negotiations.