T110-04 - Fitzsimmons Creek Habitat Compensation Channel: Phase 2 (Канада - Тендер #70907183) | ||
| ||
| Для перевода текста тендера на нужный язык воспользуйтесь приложением: | ||
Страна: Канада (другие тендеры и закупки Канада) Организатор тендера: www.merx.com Номер конкурса: 70907183 Дата публикации: 24-02-2026 Источник тендера: www.merx.com |
||
Construction services required for habitat channel restoration work including site preparation, excavation, woody debris management, and environmental compliance with migratory bird regulations.
00004916911
Issuing OrganizationResort Municipality of Whistler
Solicitation TypeRFQ - Request for Quote (Informal)
Solicitation NumberT110-04
TitleFitzsimmons Creek Habitat Compensation Channel: Phase 2
Source IDSCRIBE
British Columbia
Purchase TypeNot Stated
2026/02/24 09:51:00 AM EST
Closing Date2026/03/05 05:00:00 PM EST
Rob Mellander
rmellander@whistler.ca
Construction services to be provided will consist of:
1. Prior to work commencing, preparing equipment to be working in a habitat area by using vegetable based hydraulic oil and precleaning power washing equipment to remove excess oil and
grease.
2. Establishing construction access from Lost Lake Loop Road (location shown in Figure 1) to the work area. Construction access to the work area may require grubbing and preparation to
accommodate the heavy vehicles which would include a vehicle turn around area.
3. Staffing Traffic Control Person (TCP) locations through the duration of the project to maintain public access along the valley trail.
4. Surveying and grubbing along Phase 2 construction extents,
5. Excavation to achieve Phase 2 cut extents, and hauling to an approved disposal location, to be arranged by the contractor,
6. Stockpiling large woody debris logs and boulders removed during construction that meets material specifications.
7. Sourcing, importing, and placing additional large woody debris logs and boulders (additional logs and boulders will need to be imported).
8. Complete seeding and planting work under the direction of the construction QEP and as per Schedule B Habitat Channel Restoration Plan. 9. Bidders meeting scheduled for March 3rd at 10:00am
via the following Teams link. Meeting link
10. Construction must comply with the migratory bird nest survey window which starts in Whistler March 26 to August 17. The spring low risk window starts March 26 and May 13th. As no active
nests may be disturbed, all vegetation removal between March 26 and August 17 will be subject to the QEP conducting a nesting bird survey.
11. The RMOW will obtain regulatory and CN approvals for this work.
12. The live design load for Fitzsimmons Bridge accessing the work zone is BCL-625 rated.