GOC667304-CS - GOC667304-CS Exterior Roof Upgrade – Exterior Roof Replacements (Канада - Тендер #67525829) | ||
| ||
| Для перевода текста тендера на нужный язык воспользуйтесь приложением: | ||
Страна: Канада (другие тендеры и закупки Канада) Организатор тендера: www.merx.com Номер конкурса: 67525829 Дата публикации: 07-10-2025 Источник тендера: www.merx.com |
||
0000304281
Issuing OrganizationBGIS - PWGSC RP1
Solicitation TypeRFQ - Request for Quote (Formal)
Solicitation NumberGOC667304-CS
TitleGOC667304-CS Exterior Roof Upgrade – Exterior Roof Replacements
Source IDPU.DP.Que..8088.29965.C334327
Canada, Manitoba, All of Manitoba
Delivery PointRCMP Detachments – DBU24 Selkirk Exterior Roof Upgrade – DBU456 Pukatawagan & DBU371 The Pas
Purchase TypeOne Time Only- Delivery Date:Dec 31, 2026
Description
Scope of Work/Overview:
DBU24 Selkirk - The intent of this project is to complete exterior roof upgrades. The district office detachment is 1489 square meters. The exact requirements will need to be
provided to BGIS by RCMP MB Asset Management. As per RCMP policy outlined in PMM 3.3 Building Standards and Guidelines ("Unclassified Version"), the Fit-Up Standards will be applied to all
detachment construction, renovation, retrofit and rehabilitation projects. Roof B remains the primary area of concern due to recurring leaks despite having been replaced a few years prior. A
detailed inspection of this section shall be undertaken to ascertain the root cause of the water infiltration and to develop recommendations aimed at preventing future leakage following
replacement. The roof was replaced in 2022 as per our records. However, a separate contractor has advised BGIS that Roof Section B requires replacement again. A comprehensive inspection of the
entire roofing system—not limited to Section B—should be conducted to accurately assess its condition and determine the appropriate course of action.
DBU456 Pukatawagan & DBU371 The Pas - The intent of these projects is to replace the current flat, built-up roofs at the detachments with new. Based on the feedback and
service requests BGIS has received, the roofs are in poor condition and are leaking. Additional info for these projects regarding the restructuring component needs to be requested from RCMP MB
Asset Management. As per RCMP policy outlined in PMM 3.3 Building Standards and Guidelines (Unclassified Version), the Fit-Up Standards will be applied to all detachment construction,
renovation, retrofit and rehabilitation projects.
Projects should consider increasing the thermal performance of the roofs to meet the prescriptive thermal performance requirements of the applicable codes (ie. National Building Code, National
Energy Code for Buildings). The consultant should review existing insulation and replace if required, also the client would like to have the Technical Investigation note if a repair is
recommended rather than a full replacement, etc..
Investigate available utility incentive/rebate programs (ie. Efficiency Manitoba). A thorough inspection of the roofs will be carried out to identify the underlying cause of water infiltration
and to develop recommendations for preventing future leaks after replacement. A full evaluation of the entire roofing system should also be performed to accurately determine its current
condition and establish the necessary corrective measures.
Oct 06, 2025 11:02 AM CDT
Bid IntentNot Available
Question Acceptance DeadlineOct 10, 2025 02:00 PM CDT
Questions are submitted onlineYes
Closing DateOct 20, 2025 02:00 PM CDT
Denise Sandulak
204-333-6294
Denise.Sandulak@bgis.com
Acknowledgement
By submitting our response to this solicitation, we confirm that we have read and agree to comply with the terms and conditions of this RFQ, and we agree to provide, upon request, all
documentation without modification as defined in this RFQ. BGIS reserves the right to reject our submission should BGIS fail to receive the required documentation.
Electronic Bid Submission
PricingLump sum
Bid Documents List| Item Name | Description | Mandatory | Limited to 1 file |
|---|---|---|---|
| Bid Documents | Documents defining the proposal | Yes | No |
| No entries | |||
Please note Security Requirements
See moreProperty Management Supplier Compliance (BGIS - RP4)