AB-2025-05823 - Harlech - Shunda Creek - Youth Assessment Camp - Demolition and Remediation (Канада - Тендер #66755743) | ||
| ||
Для перевода текста тендера на нужный язык воспользуйтесь приложением: | ||
Страна: Канада (другие тендеры и закупки Канада) Организатор тендера: www.merx.com Номер конкурса: 66755743 Дата публикации: 06-09-2025 Источник тендера: www.merx.com |
||
Seeking contractor for complete demolition and site restoration of Shunda Creek Youth Camp in Clearwater County, Alberta, including hazardous materials removal, building demolition, utility decommissioning, and environmental restoration.
00004704418
Issuing OrganizationAlberta Infrastructure
Solicitation TypeITB - Invitation to Bid (Formal)
Solicitation NumberAB-2025-05823
TitleHarlech - Shunda Creek - Youth Assessment Camp - Demolition and Remediation
Source IDSCRIBE
Alberta
Purchase TypeNot Stated
2025/09/05 11:01:00 AM EDT
Closing Date2025/10/07 04:00:00 PM EDT
Mohamed Siddique
mohamed.siddique@gov.ab.ca
Work of this Contract comprises the following:
Hazardous Materials
.1 Remove asbestos-containing materials
.2 Remove other hazardous building materials
.3 Chemical removal (WHMIS/SDS compliant)
.4 Remove mercury and PCB components
Demolition and Removal
.1 Mobilization and demobilization
.2 Demolish building structures
.3 Remove underground utilities
.4 Remove site features (fencing, car plugs, etc.)
.5 Remove hard surfaces (hardstanding)
.6 Grade and backfill building area
.7 Dispose of all waste
.8 Provide traffic control as needed
.9 Document utility isolation (as-builts)
Utility Decommissioning
.1 Decommission wastewater system
.2 Decommission water system
.3 Decommission water well
Earthworks and Site Cleanup
.1 Clear and grub site
.2 Strip and stockpile topsoil
.3 Excavate and recontour camp area
.4 Dewatering of lagoon and offsite disposal of wastewater
.5 Excavation of sludge material and storing for beneficial re-use/land application
.6 Backfilling of lagoon with surrounding berm material prior to grading
.7 Land application of sludge material following soil replacement
Site Restoration
.1 Place topsoil (onsite and borrow material)
.2 Seed restored areas
.3 Treat for weed control
.4 Install erosion control (e.g., straw wattles, silt fence)
Municipal Address: Shunda Creek Youth Camp Site, Swale Road, Clearwater County, Alberta T0M 2H0.
Information/Pre-bid Meeting
Thu•Sep 11, 2025•2:00 pm (MT)